Bangalore/Project record

K-RERA · the public record

Westline Signature

· Westline Builders

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

83%construction reportedQ1 2026 filing
71units not bookedof 137 · Q1 2026 filing
137registered unitsK-RERA registration · read 16 Jul 2026

The record · free to read

Registration read 16 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Inventory & scale

What this registration contains.

4 BHK DUPLEX
9

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

1.1registered acres

130.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1257/334/PR/171021/000845

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Land area4,250 sq m (1.1 acres)
Homes registered137
Tower/wing entries1
Unit mix9 × 4 BHK DUPLEX

In context

Density130.5 homes per acre
Density in context86th percentile of 4882 projects in this register (median 82.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units137Total inventory registered with K-RERA.
Official carpet area1,849 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area4,250 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~6.56Sanctioned floor-area ratio (≈27,863 sqm sanctioned FAR area ÷ 4,250 sqm land) — higher means a denser vertical build.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)220Separate filed counts; these categories may overlap and are not added together.
Open-parking field9Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date12-04-2017

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK DUPLEX9100%1,849 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Westline Signature50137220-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 137 official flat/unit rows, matching the 137 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK5892.5-99.8 sqft0.0 sqft58
3 BHK29112.5 sqft0.0 sqft29
4 BHK+MEDIA DUPLEX22193.1 sqft0.0 sqft44
3 BHK + MEDIA DUPLEX15179.4-180.8 sqft0.0 sqft30
4 BHK DUPLEX9193.1-207.1 sqft0.0 sqft18
PENTHOUSE3304.7-508.9 sqft0.0-0.0 sqft6
3 BHK DUPLEX1179.4 sqft0.0 sqft2

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Westline Signature13792.5-508.9 sqft0.0-0.0 sqft187
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
WSI-00-1Westline Signature04 BHK+MEDIA DUPLEX193.1 sqft0.0 sqft2
WSI-01-2Westline Signature12 BHK92.5 sqft0.0 sqft1
WSI-01-3Westline Signature12 BHK99.8 sqft0.0 sqft1
WSI-01-4Westline Signature13 BHK112.5 sqft0.0 sqft1
WSI-02-1Westline Signature24 BHK+MEDIA DUPLEX193.1 sqft0.0 sqft2
WSI-02-2Westline Signature22 BHK92.5 sqft0.0 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

2 of 34 compliance document slots are filed as Not Applicable; the remaining 32 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

1 K-RERA order on this project (PROJECT MODIFICATION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
M. RAMACHANDRA vs M/S. WESTLINE CONSTRUCTIONS & DEVELOPMENTS PVT. LTD.Enclosed Below.AUTHORITY27/12/2023
MR. M. RAMACHANDRA vs M/S. WESTLINE CONSTRUCTIONS & DEVELOPMENTS PVT. LTD.,RELIEFS & COMPENSTATION CLAIMED ARE ENCLOSED BELOWAUTHORITY27/12/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectGuulshan Roy-1999Kodialbail West, Mangalore
ContractorMfar Constructions Pvt Ltd-199680 Feet Road, Koramangala
Structural engineerNikhil Shanghavi---

Builder track record

RERA filing

Westline Builders has 2 other K-RERA-registered projects in our records. 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹68.18 Cr collected from buyers, ₹111.25 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹111.25 Cr) exceeded buyer collections (₹68.18 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress77% → 83% (+6 pts)
Units sold/booked as registered66/137 (48%)
Buyer collections in available QPRs₹135.13 Cr
Escrow withdrawals in available QPRs₹323.08 Cr (2.39x collections)
  • Construction progress moved from 77% to 83% across the filed QPR window.
  • Across available QPR rows, escrow withdrawals are 2.39x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹38.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA COMMERCIAL BRANCH MANGALORE (IFSC SBIN0004118, a/c …5620). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata7 km
Kempegowda Int'l Airport13 km
MG Road / city centre15 km
Whitefield IT hub20 km
Bellandur–Marathahalli belt20 km
Electronic City29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Westline Builders.
Westline Builders has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Westline Jeppu Medicity
No filings

Other RERA-registered projects in Yelahanka

Major developers building in Yelahanka

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Westline Signature?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 16 Jul 2026