Capital Gateway
SECTOR-110A/111, VILLAGE CHAU MA, GURUGRAM · Kns Infracon
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
30 Jun 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 18 filed quarterly reports, Capital Gateway records ₹17.78 Cr paid into and ₹17.57 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹21 L.
₹17.78 Cr
into the escrow account
₹17.57 Cr
withdrawn
₹21 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2020 Q4 | 0 | 538 |
| 2021 Q1 | 0 | 538 |
| 2021 Q2 | 0 | 538 |
| 2021 Q3 | 0 | 538 |
| 2021 Q4 | 0 | 538 |
| 2022 Q1 | 0 | 538 |
| 2022 Q2 | 0 | 538 |
| 2022 Q3 | 0 | 538 |
| 2022 Q4 | 0 | 538 |
| 2023 Q1 | 3 | 538 |
| 2023 Q2 | 0 | 538 |
| 2023 Q3 | 2 | 538 |
| 2023 Q4 | 2 | 538 |
| 2024 Q1 | 3 | 538 |
| 2024 Q2 | 2 | 538 |
| 2024 Q3 | 33 | 538 |
| 2024 Q4 | 5 | 538 |
| 2025 Q1 | 0 | 538 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2020 Q4 | ₹0 L | ₹0 L | ₹0 L |
| 2021 Q1 | ₹0 L | ₹0 L | ₹0 L |
| 2021 Q2 | ₹0 L | ₹0 L | ₹0 L |
| 2021 Q3 | ₹0 L | ₹0 L | ₹0 L |
| 2021 Q4 | ₹0 L | ₹0 L | ₹0 L |
| 2022 Q1 | ₹0 L | ₹0 L | ₹0 L |
| 2022 Q2 | ₹0 L | ₹0 L | ₹0 L |
| 2022 Q3 | ₹0 L | ₹0 L | ₹0 L |
| 2022 Q4 | ₹0 L | ₹0 L | ₹0 L |
| 2023 Q1 | ₹51 L | ₹0 L | ₹51 L |
| 2023 Q2 | ₹32 L | ₹83 L | ₹0 L |
| 2023 Q3 | ₹3 L | ₹0 L | ₹3 L |
| 2023 Q4 | ₹18 L | ₹0 L | ₹21 L |
| 2024 Q1 | ₹17 L | ₹0 L | ₹38 L |
| 2024 Q2 | ₹0 L | ₹28 L | ₹10 L |
| 2024 Q3 | ₹3.65 Cr | ₹2.41 Cr | ₹1.34 Cr |
| 2024 Q4 | ₹5.47 Cr | ₹4.98 Cr | ₹1.83 Cr |
| 2025 Q1 | ₹7.45 Cr | ₹9.07 Cr | ₹21 L |
Location & Connectivity
The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Udyog Vihar | 5 km |
| Cyber City / DLF Cyber Hub | 6 km |
| IGI Airport, Delhi | 8 km |
| Golf Course Road belt | 11 km |
| IMT Manesar | 20 km |
| Connaught Place, Delhi | 22 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.