HRERA · the public record
M3m Capital
SECTOR -113, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA. · Union Buildmart
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
29 Jun 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 12 filed quarterly reports, M3m Capital records ₹292.69 Cr paid into and ₹339.52 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹4.17 Cr.
₹292.69 Cr
into the escrow account
₹339.52 Cr
withdrawn
₹4.17 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2023 Q2 | 15 | 750 |
| 2023 Q3 | 13 | 750 |
| 2023 Q4 | 12 | 750 |
| 2024 Q1 | 3 | 750 |
| 2024 Q2 | 2 | 750 |
| 2024 Q3 | 6 | 750 |
| 2024 Q4 | 4 | 750 |
| 2025 Q1 | 4 | 750 |
| 2025 Q2 | 1 | 750 |
| 2025 Q3 | 5 | 750 |
| 2025 Q4 | 1 | 750 |
| 2026 Q1 | 2 | 750 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2023 Q2 | ₹41.29 Cr | ₹41.00 Cr | ₹51.29 Cr |
| 2023 Q3 | ₹5.36 Cr | ₹0 L | ₹56.65 Cr |
| 2023 Q4 | ₹47.30 Cr | ₹95.79 Cr | ₹8.16 Cr |
| 2024 Q1 | ₹25.47 Cr | ₹28.19 Cr | ₹5.44 Cr |
| 2024 Q2 | ₹17.91 Cr | ₹17.44 Cr | ₹5.91 Cr |
| 2024 Q3 | ₹3.41 Cr | ₹3.61 Cr | ₹5.71 Cr |
| 2024 Q4 | ₹61.66 Cr | ₹63.38 Cr | ₹4.00 Cr |
| 2025 Q1 | ₹4.89 Cr | ₹5.25 Cr | ₹3.64 Cr |
| 2025 Q2 | ₹41.10 Cr | ₹38.75 Cr | ₹5.99 Cr |
| 2025 Q3 | ₹38.68 Cr | ₹40.65 Cr | ₹4.02 Cr |
| 2025 Q4 | ₹3.75 Cr | ₹3.70 Cr | ₹4.08 Cr |
| 2026 Q1 | ₹1.85 Cr | ₹1.75 Cr | ₹4.17 Cr |
Builder Record
Union Buildmart has 5 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 2 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- M3m Capital Phase-2 — declared 2026-12-31 · OC on record
- M3m Capital Phase-3 — declared 2028-02-29 · OC on record
- M3m Mansion — declared 2030-03-31
- M3m Mansion Ph-2 — declared 2031-02-28
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Udyog Vihar | 6 km |
| Cyber City / DLF Cyber Hub | 7 km |
| IGI Airport, Delhi | 8 km |
| Golf Course Road belt | 12 km |
| IMT Manesar | 20 km |
| Connaught Place, Delhi | 22 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.