Elan Empire
REVENUE ESTATE VILLAGE MAIDAW AS , SECTOR-66 , GURUGRAM , HARYANA · Elan City
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
14 Apr 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 9 filed quarterly reports, Elan Empire records ₹181.86 Cr paid into and ₹179.88 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹0 L.
₹181.86 Cr
into the escrow account
₹179.88 Cr
withdrawn
₹0 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Official Unit Inventory
312 apartments filed across 4 carpet-area configurations, 6 towers, carpet areas from 274 to 52,828 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).
| Carpet area | (metric) | Units of this size |
|---|---|---|
| 4,999 sq ft | 464.4 sq m | 2 |
| 730 sq ft | 67.8 sq m | 2 |
| 491 sq ft | 45.6 sq m | 3 |
| 274 sq ft | 25.4 sq m | 2 |
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2021 Q4 | 155 | 624 |
| 2022 Q1 | 94 | 312 |
| 2022 Q2 | 20 | 312 |
| 2022 Q3 | 0 | — |
| 2022 Q4 | 19 | 312 |
| 2023 Q1 | 3 | 312 |
| 2023 Q2 | 0 | 312 |
| 2023 Q3 | 8 | 351 |
| 2023 Q4 | 1 | 351 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2021 Q4 | ₹72.33 Cr | ₹71.46 Cr | ₹1.74 Cr |
| 2022 Q1 | ₹65.37 Cr | ₹64.09 Cr | ₹1.64 Cr |
| 2022 Q2 | ₹13.17 Cr | ₹13.44 Cr | ₹1.37 Cr |
| 2022 Q3 | ₹10.80 Cr | ₹11.12 Cr | ₹1.05 Cr |
| 2022 Q4 | ₹3.93 Cr | ₹4.82 Cr | ₹16 L |
| 2023 Q1 | ₹2.72 Cr | ₹2.15 Cr | ₹73 L |
| 2023 Q2 | ₹1.96 Cr | ₹1.23 Cr | ₹0 L |
| 2023 Q3 | ₹7.84 Cr | ₹7.84 Cr | ₹0 L |
| 2023 Q4 | ₹3.74 Cr | ₹3.73 Cr | ₹0 L |
Builder Record
Elan has 25 other Gurgaon projects on the HRERA register; 1 is past the declared completion date with no OC yet, 9 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Aspen One — declared 2031-06-30
- Commercial Colony — declared 2023-09-13 · OC on record
- Commercial Project — declared 2022-09-13 · OC on record
- Elan Empire — declared 2028-04-30
Location & Connectivity
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Golf Course Road belt | 7 km |
| Cyber City / DLF Cyber Hub | 11 km |
| Udyog Vihar | 12 km |
| IMT Manesar | 13 km |
| IGI Airport, Delhi | 18 km |
| Connaught Place, Delhi | 30 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.