HRERA · the public record
Trump Towers Delhi Ncr
SECTOR-65, GURUGRAM, HARYANA · Olive Realcon
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
28 Jun 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 11 filed quarterly reports, Trump Towers Delhi Ncr records ₹851.55 Cr paid into and ₹857.72 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹28 L.
₹851.55 Cr
into the escrow account
₹857.72 Cr
withdrawn
₹28 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2023 Q4 | 2 | 262 |
| 2024 Q1 | 0 | 262 |
| 2024 Q2 | 10 | 262 |
| 2024 Q3 | 11 | 262 |
| 2024 Q4 | 1 | 262 |
| 2025 Q1 | 1 | 262 |
| 2025 Q2 | 0 | 262 |
| 2025 Q3 | 1 | 262 |
| 2025 Q4 | 5 | 262 |
| 2026 Q1 | 0 | 262 |
| 2026 Q2 | 5 | 262 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2023 Q4 | ₹39.18 Cr | ₹34.44 Cr | ₹11.18 Cr |
| 2024 Q1 | ₹61.16 Cr | ₹58.70 Cr | ₹13.65 Cr |
| 2024 Q2 | ₹55.47 Cr | ₹60.61 Cr | ₹8.51 Cr |
| 2024 Q3 | ₹185.84 Cr | ₹188.25 Cr | ₹6.10 Cr |
| 2024 Q4 | ₹132.01 Cr | ₹133.50 Cr | ₹4.61 Cr |
| 2025 Q1 | ₹24.25 Cr | ₹28.35 Cr | ₹51 L |
| 2025 Q2 | ₹17.62 Cr | ₹17.37 Cr | ₹76 L |
| 2025 Q3 | ₹227.84 Cr | ₹224.80 Cr | ₹3.79 Cr |
| 2025 Q4 | ₹82.86 Cr | ₹86.30 Cr | ₹35 L |
| 2026 Q1 | ₹20.48 Cr | ₹20.59 Cr | ₹24 L |
| 2026 Q2 | ₹4.85 Cr | ₹4.81 Cr | ₹28 L |
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Golf Course Road belt | 6 km |
| Cyber City / DLF Cyber Hub | 11 km |
| Udyog Vihar | 11 km |
| IMT Manesar | 14 km |
| IGI Airport, Delhi | 18 km |
| Connaught Place, Delhi | 29 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.