Tulip Purple Phase 2
SECTOR-69-70, GURUGRAM · Tulip Infratech
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
30 Dec 2023
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 12 filed quarterly reports, Tulip Purple Phase 2 records ₹23.00 Cr paid into and ₹22.58 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹0 L.
₹23.00 Cr
into the escrow account
₹22.58 Cr
withdrawn
₹0 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2020 Q4 | 0 | 80 |
| 2021 Q1 | 1 | 80 |
| 2021 Q2 | 0 | 80 |
| 2021 Q3 | 0 | 80 |
| 2021 Q4 | 6 | 80 |
| 2022 Q1 | 7 | 80 |
| 2022 Q2 | 13 | 80 |
| 2022 Q3 | 6 | 80 |
| 2022 Q4 | 9 | 80 |
| 2023 Q1 | 3 | 80 |
| 2023 Q2 | 0 | 80 |
| 2023 Q3 | 0 | — |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2020 Q4 | ₹0 L | ₹0 L | ₹0 L |
| 2021 Q1 | ₹0 L | ₹0 L | ₹0 L |
| 2021 Q2 | ₹7 L | ₹0 L | ₹7 L |
| 2021 Q3 | ₹15 L | ₹21 L | ₹1 L |
| 2021 Q4 | ₹63 L | ₹61 L | ₹3 L |
| 2022 Q1 | ₹66 L | ₹67 L | ₹2 L |
| 2022 Q2 | ₹11.57 Cr | ₹11.55 Cr | ₹4 L |
| 2022 Q3 | ₹2.98 Cr | ₹2.90 Cr | ₹13 L |
| 2022 Q4 | ₹5.12 Cr | ₹5.10 Cr | ₹15 L |
| 2023 Q1 | ₹1.81 Cr | ₹1.54 Cr | ₹42 L |
| 2023 Q2 | ₹0 L | ₹0 L | ₹0 L |
| 2023 Q3 | ₹0 L | ₹0 L | ₹0 L |
Builder Record
Tulip Infratech has 6 other Gurgaon projects on the HRERA register; 1 is past the declared completion date with no OC yet, 1 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Tulip Crimson — declared 2032-03-31
- Tulip Lemon — declared 2019-11-23 · OC on record
- Tulip Monsella and Tulip Attila — declared 2030-12-31
- Tulip Violet — declared 2032-12-30
Location & Connectivity
The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Golf Course Road belt | 8 km |
| IMT Manesar | 11 km |
| Cyber City / DLF Cyber Hub | 12 km |
| Udyog Vihar | 13 km |
| IGI Airport, Delhi | 19 km |
| Connaught Place, Delhi | 31 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.