Mumbai/Project record

MahaRERA · the public record

AARYA BY MANGAL

Vile Parle (West) · MANGAL BUILDHOME PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2028declared completionMahaRERA registration · read 12 Jul 2026
3registered unitsMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1180002600023

Delivery and registration

When is the project declared for completion?

AARYA BY MANGAL is registered with MahaRERA as PR1180002600023 and the promoter has declared completion for 31 Mar 2028.

31 Mar 2028

declared completion

18months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPR1180002600023
Registered on06 Apr 2026
Promoter-declared completion31 Mar 2028
Current statusCertificate Signed
Against today18 months to the declared date

Promoter record

What else is this promoter on record for?

Mangal Buildhome is the promoter of record on 16 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In AARYA BY MANGAL, ₹1.49 Cr of a declared ₹5.62 Cr estimated project cost is reported as incurred, about 26.6%, as at the last certified filing with MahaRERA.

26.6%

₹1.49 Cr

of ₹5.62 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AARYA BY MANGAL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 3 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
PROPOSED BUILDING ON PLOT BEARING CTS NO. 676 OF VILLAGE JUHU AT N.S. ROAD NO. 8, JVPD SCHEME, JUHU, MUMBAI.1G+53-

Unit mix on the filing: 3 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Vile Parle (West), CTS Nos. 676, Plot No.69, N.S. Road no.8, Andheri, Mumbai Suburban, 400049. Per the filed land record, the plot is bounded to the north by CTS NO. 678 , to the south by CTS NO. 675, to the east by N.S Road No. 8 and to the west by CTS NO. 658. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport4 km
Andheri MIDC / SEEPZ5 km
Bandra Kurla Complex (BKC)6 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mangal Buildhome Private Limited is the promoter on 7 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Mangal Buildhome Private Limited project & its RERA track record →

Other flagged projects by Mangal Buildhome Private Limited

Mangal Buildhome Private Limited
Deregistered by MahaRERAMumbai Suburban
Mangal Buildhome Private Limited
FlaggedMumbai Suburban
Mangal Buildhome Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Juhu

Elenora
possession by Sep 2026 · Parinee VIR Bhuvan Redevelopment Private
K L Valeria
possession by Sep 2026 · K L Housing LLP
Valletta
possession by Sep 2026 · K Raheja Corp Real Estate Private Limite
Maestro
possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Aditya Chsl
possession by Dec 2026 · Shree Mahavir Developers
Gurukrupa Alaknanda
possession by Dec 2026 · Gurukrupa Realcon Infrastructure Develop

Major developers building in Juhu

Other RERA-registered projects in Mumbai Suburban

Aasamanta Laxmi Narayan
possession by Mar 2028 · Aasamanta Realty
Aasamanta White House
possession by Mar 2028 · Aasamanta Realty
Aashirwad
declared completion Dec 2025 · Aashirwad Constructions
Aashray
declared completion Dec 2022 · Vintage Enterprises
Aashray
possession by Dec 2027 · Creative Builders
Aatman
possession by Oct 2028 · Gurukrupa Realcon Builders AND Developer

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026