31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900078648

Delivery and registration

When is the project declared for completion?

AETHERIA TOWER is registered with MahaRERA as P51900078648 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900078648
Registered on30 Dec 2024
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AETHERIA TOWER record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AETHERIA TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
BLDG NO 1-B WING1G+13-
BLDG NO 1-A WING1G+21-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at LOWER PAREL, N.M.JOSHI MARG, Mumbai City, Mumbai City, 400013. Per the filed land record, the plot is bounded to the north by 830, to the south by 828, to the east by 830 and to the west by BY ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lower Parel

Akshay
possession by Dec 2026 · Lalitambika Builders & Developers Pr
Sarvesh ONE
possession by Dec 2026 · Sarvesh Urban Developers Private Limited
Adi Darsshan
possession by Dec 2026 · Adi Realtors
Siddharth Enclave
possession by Dec 2026 · Siddharth Developers
THE Auro
possession by Nov 2027 · Alamdar Infrastructure PVT LTD
Arihant Towers - BY MJ Shah
possession by Dec 2027 · Zeus Housing Company

Major developers building in Lower Parel

Other RERA-registered projects in Mumbai City

Ahilya
declared completion Jan 2022 · Square Nine Abodes
Aikya Heights
declared completion Dec 2024 · Aikya Realty PVT LTD
Ajinkyatara
declared completion Dec 2017 · Bhalchandra Vinayak Wadnerkar
Ajmal-235
possession by Jul 2029 · Awfi Real Estate Private Limited
Ajmera Downtown
possession by Dec 2027 · Ashjit Realties Pvt. Ltd.
Akanksha
declared completion Dec 2024 · Rupji Constructions

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.