Mumbai/Project record

MahaRERA · the public record

AMESH CHS LTD

Mumbai Suburban · RIGHT CHANNEL CONSTRUCTION PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007597

Delivery and registration

When is the project declared for completion?

AMESH CHS LTD is registered with MahaRERA as P51800007597 and the promoter has declared completion for 30 Jun 2018.

30 Jun 2018

declared completion

99months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007597
Registered on17 Aug 2017
Promoter-declared completion30 Jun 2018
Current statusCertificate Signed
Against todayabout 99 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AMESH CHS LTD record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Right Channel Construction is the promoter of record on 8 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AMESH CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
AMESH CHS LTDB WING1G+830 Jun 2018
AMESH CHS LTD A WING1G+1530 Jun 2018

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for AMESH CHS LTD, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000016136511/11/2019Rekha Patel vs Right Channel constructions pvt ltdorder passed

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by BUILDING NO 44WESTWIDE ROAD, to the south by SWEEPER COTTAGE, to the east by BUILDING NO43 and to the west by BUILDING NO 45. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district10 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Right Channel Construction PVT LTD is the promoter on 6 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Right Channel Construction PVT LTD

Right Channel Construction PVT LTD
FlaggedMumbai Suburban
Right Channel Construction PVT LTD
FlaggedMumbai Suburban
Right Channel Construction PVT LTD
FlaggedMumbai Suburban
Right Channel Construction PVT LTD
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Chembur

Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited
Laxmina Krishna Niwas
possession by Oct 2026 · Laxmina Argentum Realties Private Lim
Safal SAI AND Safal Sainath
possession by Oct 2026 · Mangalnath Developers PVT LTD

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Amey Apartments
possession by Oct 2026 · Amey Realty AND Construction LLP
Ameya Residency
possession by Dec 2029 · Ameya Realtors Private Limited
Amin Alturas
declared completion Sep 2020 · AVD Developers
Amore Edge
declared completion Dec 2025 · Gmheightsllp
Ampple-ONE
possession by Mar 2027 · Amppletech Projects Private Limited
Amrapali
declared completion Dec 2021 · Mangal Buildhome Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026