MahaRERA Property Intelligence · Thane

AMIZRA

P51700006965 · Vartak Nagar · promoter Jagdale Infrastructure Pvt

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51700006965
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Jagdale Infrastructure Pvt is the promoter of record on 19 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+32.

BuildingWingsFloorsDeclared completion
AMIZRA B1G+3216 Dec 2019
AMIZRA A1G+230 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202231 Dec 2021The scheduled delivery date of Project-Amizra was 31/12/2018, however it could be delayed possibly due to certain Policy changes made by the state during the execution of the proje
30 Dec 202231 Dec 2021The revised delivery date of Project-Amizra was 31/12/2019. We have completed construction and applied for OC of proposed Residential Building B (UG+LG+S+29) and are awaiting for i

Location, Land & Connectivity

Located at Vartak Nagar, Kores road, Thane, Thane, 400606. Per the filed land record, the plot is bounded to the north by DOSTI VIHAR, to the south by NALLA, to the east by DOSTI VIHAR and to the west by 20 M WIDE DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ13 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)18 km
Lower Parel / Worli business district27 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Jagdale Infrastructure Pvt. Ltd. is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Jagdale Infrastructure Pvt. Ltd.

Jagdale Infrastructure Pvt. Ltd.
FlaggedThane
Jagdale Infrastructure Pvt. Ltd.
FlaggedThane
Jagdale Infrastructure Pvt. Ltd.
FlaggedThane
Jagdale Infrastructure Pvt. Ltd.
FlaggedMumbai Suburban

Other RERA-registered projects in Thane

TEN X Habitat Raymond Realty Tower F
possession by Aug 2026 · Raymond Realty Limited
Shreesandesh Heights
possession by Sep 2026 · Aditya Enterprises
Elito Grand Central
possession by Dec 2026 · Fortune Infracreators Private Limited
Glorio Grand Central
possession by Dec 2026 · Ekdant Constructions And Developers Priv
Stella Grand Central
possession by Dec 2026 · Fortune Infracreators Private Limited
Tresora Grand Central
possession by Dec 2026 · Fortune Infracreators Private Limited

Other RERA-registered projects in Thane

Ammar Meadows
declared completion Dec 2021 · Meenar Associates
Ammar Meadows Phase 2
declared completion Jun 2018 · Meenar Associates
Ammu Co-Op Housing Society Ltd
possession by Mar 2027 · Stonecrafters
Amogh Ratan
possession by Dec 2026 · Aashish Krishanarao Pathare
Amol Saubhagya
possession by Mar 2028 · Suman Realties
Amor Estate
declared completion Jun 2026 · Shailesh Jamnadas Dawda

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026