MahaRERA Property Intelligence · Mumbai Suburban
P51800006653 · mulund east · promoter Amardeep Constructions
| MahaRERA registration | P51800006653 |
| Registered on | 16 Aug 2017 |
| Promoter-declared completion | 30 Jun 2023 |
| Current status | Certificate Signed |
| Against today | about 37 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Amardeep Constructions is the promoter of record on 6 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+29.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Sale building no 1 | 1 | G+4 | - |
| Building 3 Rehab Parampujya Dr Babasaheb Ambedkar Nagar SRA CHS Ltd A to D Wing | 1 | G+19 | - |
| Building no 4 Rehab Parampujya Dr Babasaheb Ambedkar Nagar SRA CHS Ltd A Wing | 1 | G+21 | - |
| ANUTHAM A, B, D,E WING ,C WING-VEENA | 1 | G+29 | 31 May 2020 |
32 complaints are on the MahaRERA record for this project, with orders passed in 27. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000210017 | 14/02/2022 | Sachin Dhyaneshwar More vs M/s. Amardeep Constructions | order passed |
| CC006000000193396 | 08/07/2020 | Gaurav Kirit Vithlani vs Amardeep Constructions | order passed |
| CC006000000193397 | 08/07/2020 | Kirit K. Vithlani vs Amardeep Constructions | order passed |
| CC006000000198895 | 31/10/2021 | DEEPALI LOHOT vs AMARDEEP CONSTRUCTIONS | order passed |
| CC006000000198896 | 01/11/2021 | PRAFUL VILAS PATIL vs AMARDEEP CONSTRUCTIONS | order passed |
| CC006000000198898 | 31/10/2021 | Poornima Patil vs Anutham Constructions | order passed |
| CC006000000198899 | 01/11/2021 | SACHIN RAMCHANDRA CHAVAN vs AMARDEEP CONSTRUCTIONS | order passed |
| CC006000000198906 | 01/11/2021 | rajesh devji chamaria vs ANUTHAM CONSTRUCTION | order passed |
| CC006000000198908 | 01/11/2021 | DEEPAK KURLE vs ANUTHAM CONSTRUCTIONS | order passed |
| CC006000000198909 | 01/11/2021 | ANAND CHANDRAKANT AGRAWAL vs ANUTHAM CONSTRUCTIONS | order passed |
| CC006000000198924 | 03/11/2021 | VISHAKA VILAS SHINDE vs ANUTHAM CONSTRUCTIONS | order passed |
| CC006000000198925 | 03/11/2021 | SONALI KANDALKAR vs M/S Amardeep Constructions | order passed |
| CC006000000198927 | 03/11/2021 | Atul Parashuram Thamake vs Amardeep Constructions | order passed |
| CC006000000198928 | 04/11/2021 | Radha Keshav Chavan vs Amardeep Constructions | order passed |
| CC006000000198933 | 06/11/2021 | ATUL SHIRODKAR vs AMARDEEP CONSTRUCTIONS | order passed |
| CC006000000198934 | 05/11/2021 | ATUL SHIRODKAR vs AMARDEEP CONSTRUCTIONS | order passed |
| CC006000000198935 | 05/11/2021 | SUSHANT CHAVAN vs AMARDEEP CONSTRUCTIONS | order passed |
| CC006000000198937 | 05/11/2021 | Manoj Desai vs AMARDEEP CONSTRUCTIONS | order passed |
| CC006000000303568 | 06/12/2022 | AjitKumar Birendranath Ojha vs M/s Amardeep Constructions | order passed |
| CC006000000396592 | 06/07/2023 | Amol Deshpande vs Amardeep Constructions | order passed |
| CC006000000408346 | 06/12/2023 | Hirak Kishor Shah vs M/S Amardeep Constructions | order passed |
| CC006000000439632 | 12/03/2024 | Aditi Arvind Dani vs Amardeep Constructions | order passed |
| CC006000000480377 | 08/05/2024 | M/s. Amardeep Constructions vs Atul Shirodkar | order passed |
| CC006000000480385 | 08/05/2024 | M/s. Amardeep Constructions vs Atul Shirodkar | order passed |
| CC006000000480387 | 08/05/2024 | M/s. Amardeep Constructions vs Ajitkumar Birendranath Ojha | order passed |
| CC12502972 | 23/08/2025 | Praveen Ramchand Budhrani vs AMARDEEP CONSTRUCTIONS | order passed |
| CC12503442 | 26/09/2025 | Sachin Dnyaneshwar More vs AMARDEEP CONSTRUCTIONS | order passed |
| CC12600150 | 09/01/2026 | Kunal Lahu Bhor vs AMARDEEP CONSTRUCTIONS | pending / no order on file |
| CC12600753 | 09/02/2026 | Gopal Dinkar Khatke vs AMARDEEP CONSTRUCTIONS | pending / no order on file |
| CC12602352 | 21/04/2026 | AMARDEEP CONSTRUCTIONS vs Mr Uttam Suryakant Tamhanekar | pending / no order on file |
| CC12603392 | 03/06/2026 | Om Khemraj Gahlot vs AMARDEEP CONSTRUCTIONS | pending / no order on file |
| CC12603393 | 03/06/2026 | Om Khemraj Gahlot vs AMARDEEP CONSTRUCTIONS | pending / no order on file |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Jun 2023 | 31 Dec 2022 | 1) Due to current pandemic situation arising due to COVID-19, the progress of construction activities have been severely impacted and the site activities completely stopped during |
Located at mulund east, 90 feet road, Mumbai City, Mumbai City, 400081. Per the filed land record, the plot is bounded to the north by CTS 1123A2A 1123A2B 1123B 1123A11 ETC, to the south by CTS NO 1289 1293 1295 AND 1296, to the east by CTS NO 1262 1252 1127 1128 1129A 1130 AND 1131 and to the west by CTS NO 11142F 11144A AND 11144B. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 8 km |
| Andheri MIDC / SEEPZ | 10 km |
| Chhatrapati Shivaji Int'l Airport | 13 km |
| Bandra Kurla Complex (BKC) | 14 km |
| Lower Parel / Worli business district | 23 km |
| Nariman Point / Fort | 30 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in ANUTHAM?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026