MahaRERA Property Intelligence · Mumbai City

ANZAR ELEGANCE

P51900012009 · promoter Mithila Developers

Certificate SignedDue 30 Dec 2028

Delivery & Registration

MahaRERA registrationP51900012009
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mithila Developers is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~50.4% of the estimated project cost incurred as of the last certificate (₹28.04 Cr spent against a ₹55.60 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 30 homes filed with MahaRERA, 0 are sold/booked and 30 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Note: the project registers 65 homes in total, but this sold/unsold inventory filing covers only 30 of them — the other 35 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 101001651 sqft (60.5 sqm)₹1.22 Cr
Floor 111101651 sqft (60.5 sqm)₹1.27 Cr
Floor 121201651 sqft (60.5 sqm)₹1.27 Cr
Floor 131301234 sqft (21.78 sqm)₹45.84 Lakh
Floor 131306234 sqft (21.78 sqm)₹45.84 Lakh
Floor 131307651 sqft (60.5 sqm)₹1.27 Cr
Floor 1414021,119 sqft (103.97 sqm)₹2.19 Cr
Floor 1414031,119 sqft (103.97 sqm)₹2.19 Cr
Floor 151501234 sqft (21.78 sqm)₹45.84 Lakh
Floor 151502406 sqft (37.68 sqm)₹79.30 Lakh
Floor 151505407 sqft (37.79 sqm)₹79.54 Lakh
Floor 151506234 sqft (21.78 sqm)₹45.84 Lakh
Floor 161601234 sqft (21.78 sqm)₹45.84 Lakh
Floor 161606234 sqft (21.78 sqm)₹45.84 Lakh
Floor 161607651 sqft (60.5 sqm)₹1.27 Cr
Floor 171701234 sqft (21.78 sqm)₹45.84 Lakh
Floor 171706234 sqft (21.78 sqm)₹45.84 Lakh
Floor 171707651 sqft (60.5 sqm)₹1.27 Cr
Floor 181801234 sqft (21.78 sqm)₹45.84 Lakh
Floor 181806234 sqft (21.78 sqm)₹45.84 Lakh
Floor 181807651 sqft (60.5 sqm)₹1.27 Cr
Floor 191901651 sqft (60.5 sqm)₹1.27 Cr
Floor 1919021,119 sqft (103.97 sqm)₹2.19 Cr
Floor 1919031,119 sqft (103.97 sqm)₹2.19 Cr
Floor 202001651 sqft (60.5 sqm)₹1.27 Cr
Floor 2020021,119 sqft (103.97 sqm)₹2.19 Cr
Floor 2020031,119 sqft (103.97 sqm)₹2.19 Cr
Floor 212101755 sqft (70.15 sqm)₹1.54 Cr
Floor 88031,249 sqft (116 sqm)₹2.33 Cr
Floor 9901651 sqft (60.5 sqm)₹1.22 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24 and 65 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ANZAR ELEGANCE1G+2465-

Unit mix on the filing: 63 residential and 2 non-residential (shops/offices).

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250268301/08/2025Lavinha Sneha Rosario vs MITHILA DEVELOPERSpending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Bombay700/20172017Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Dec 2022Due to Covid Issue the Project could not get completed hence we are requesting you that kindly provide us the extention of on the project.
30 Dec 202130 Dec 2028a. The progress of the project was significantly impacted by a series of unforeseen challenges, primarily arising from the COVID-19 pandemic and its aftermath. Between March 2020 a

Location, Land & Connectivity

Located at Agripada West Estate , Mumbai City, Mumbai City, 400008. Per the filed land record, the plot is bounded to the north by MOMIN MANJIL, to the south by TAIBA RESIDENCY, to the east by AGRIPADA CHAWL STREET and to the west by YMCA SWIMING POOL. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Nariman Point / Fort5 km
Bandra Kurla Complex (BKC)12 km
Chhatrapati Shivaji Int'l Airport14 km
Powai / Hiranandani business park19 km
Andheri MIDC / SEEPZ19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Byculla

Kings Tower
possession by Sep 2026 · Mohammed Eshaq ALI Vadgama
Shelaji Avenues
possession by Dec 2026 · Ashirwad Shelaji Developers LLP
Al - Haram Residency
possession by Dec 2026 · M/s K. S. Hind Developers
Baug E Umar
possession by Dec 2026 · Mahanagar Constructions Private Limited
Golden Residency
possession by Dec 2026 · Golden Realty
Lakadawala Heights
possession by Dec 2026 · Aariaash Developers

Major developers building in Byculla

Other RERA-registered projects in Mumbai City

Aplite Sapphire
possession by Dec 2028 · Aplite Developers LLP
Aqdas Residency
possession by Dec 2027 · M/s. Alamdar Kapde Developer
Aqua BAY
possession by Dec 2028 · Chamunda Infrastructure Limited
AR-Rayyan
declared completion Dec 2021 · Nssr Group
Arab Building
declared completion Dec 2025 · Bhagwan Palav & Sons
Araia
possession by Dec 2027 · Kavita Dimension LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026