MahaRERA Property Intelligence · Mumbai Suburban

ARHAM ARYA

P51800049525 · NEAR AHOBILA MATH, CHEMBUR EAST · promoter Mahavir Enterprises

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51800049525
Registered on15 Feb 2023
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mahavir Enterprises is the promoter of record on 125 projects, of which 9 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~69.3% of the estimated project cost incurred as of the last certificate (₹26.35 Cr spent against a ₹38.04 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 21 homes filed with MahaRERA, 15 are sold/booked (11 with registered agreements + 4 booked) and 6 remain available (~71% sold) — selling steadily. Buyers have committed ₹45.54 Cr in agreement value so far. Of that, ₹26.51 Cr (~58%) is already collected, ₹19.04 Cr receivable — a read on how far along these sales really are. Note: the project registers 49 homes in total, but this sold/unsold inventory filing covers only 21 of them — the other 28 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 15 registered agreements, the effective carpet rate is ₹29,638/sqft (typical range ₹25,985–₹34,714) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1111011,757 sqft (163.19 sqm)₹3.32 Cr
Floor 1212011,757 sqft (163.19 sqm)₹3.32 Cr
Floor 1313031,200 sqft (111.44 sqm)₹2.26 Cr
Floor 1414011,047 sqft (97.27 sqm)₹1.98 Cr
Floor 1414031,200 sqft (111.44 sqm)₹2.26 Cr
Floor 66041,164 sqft (108.1 sqm)₹2.20 Cr

⚠ The inventory filing also declares: 11 reserved. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9 and 49 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ARHAM ARYA1G+949-

Unit mix on the filing: 49 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202531 Dec 2026We would like to request an extension for the Project Arham Arya, located at Plot No. 1361, Road No 6. Chembur East, Mumbai 400071, with Registration No. P51800049525. The project

Location, Land & Connectivity

Located at NEAR AHOBILA MATH, CHEMBUR EAST , 6th ROAD, Kurla, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by CTS NO 1365, to the south by CTS NO 1360, to the east by CTS NO 1363 and to the west by 6th ROAD CHEMBUR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Lower Parel / Worli business district10 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mahavir Enterprises is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Mahavir Enterprises project & its RERA track record →

Other flagged projects by Mahavir Enterprises

Mahavir Enterprises
FlaggedMumbai Suburban
Mahavir Enterprises
FlaggedMumbai Suburban

Other RERA-registered projects in Chembur

Chembur Deep Jyoti CHS LTD
possession by Jul 2026 · P M Developers
Hubtown Seasons - B Wing
possession by Jul 2026 · Joynest Premises Privatelimited
Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Arham Aryan
possession by Dec 2026 · Trinity Builders
Arham Aum
declared completion Dec 2017 · Mahavir Enterprises
Arham Brindavan
declared completion Dec 2017 · Mahavir Enterprises
Arham Heights - Purvi Shah And Others
declared completion Mar 2023 · Arham Heights
Arham Heritage
possession by Jan 2029 · Arham Glocal LLP
Arham Mourya
possession by Dec 2026 · Mahavir Millennium LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026