ASHISH SEA VIEW

Mumbai City · SANGHVI GRUHA NIRAMAN PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900009877

Delivery and registration

When is the project declared for completion?

ASHISH SEA VIEW is registered with MahaRERA as P51900009877 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900009877
Registered on22 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ASHISH SEA VIEW record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sanghvi Gruha Niraman is the promoter of record on 48 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

48projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ASHISH SEA VIEW in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
ASHISH SEA VIEW1G+1731 Dec 2020

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for ASHISH SEA VIEW, with orders passed in 7 of them.

7complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000004413126/06/2018MORRIS PROPERTIES PVT. LTD. vs Nimish Voraorder passed
CC00600000005641903/10/2018KAVYA BUILDCON PVT LTD vs MORRIS PROPERTIES PVT LTDorder passed
CC00600000008965615/06/2019Kamlesh A. Seth duly Constituted attorney of Dr. Pradeep Mehta vs Sanghvi Gruha Nirman Pvt. Ltd.order passed
CC00600000029280324/09/2022SHASHANK MADHUKAR NAGWEKAR vs SANGHVI GRUHA NIRAMAN PVT. LTD.order passed
CC00600000030313731/10/2022Jignesh Vora vs Sanghvi Gruh Nirman Private Limitedorder passed
CC00600000048006416/04/2024Manoj Thakur vs Raoji Shivram Raneorder passed
SM1250004904/04/2025Prabhash Tiwari vs SANGHVI GRUHA NIRAMAN PRIVATE LIMITEDorder passed

Legal & Litigation

The promoter has declared 15 court cases on this project to MahaRERA. 15 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court67152001Pending
City Civil Court47562002Pending
City Civil Court47572002Pending
City Civil Court47582002Pending
High Court24492016Pending
High Court24452016Pending
High Court24482016Pending
High Court24462016Pending
High Court24442016Pending
High Court24432016Pending
High Court24532016Pending
High Court25812016Pending
High Court25792016Pending
High Court24692016Pending
High Court24092016Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400025. Per the filed land record, the plot is bounded to the north by 40 FEET WIDE HATISKARWADI MARG, to the south by ICE CREAM FACTORY, to the east by MTNL BUILDING and to the west by AADISH SOCIETY. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Bandra Kurla Complex (BKC)7 km
Chhatrapati Shivaji Int'l Airport9 km
Nariman Point / Fort10 km
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Prabhadevi

1515 Moneco
possession by Sep 2026 · Lloyds Realty Developers Limited
25 South Tower A 11th To 47th Floor
possession by Dec 2026 · Twenty Five South Realty Limited
25 South Tower A Upto 10th Floor
possession by Dec 2026 · Twenty Five South Realty Limited
25 South - Central Tower
Deregistered by MahaRERA · possession by Dec 2028 · Twenty Five South Realty Limited
Kshitij Omkar
possession by Nov 2030 · Omkar CHS Ltd
Vakratunda Crest
possession by Dec 2030 · Inclineestate Properties LLP

Major developers building in Prabhadevi

Other RERA-registered projects in Mumbai City

Atlanta Estate Extension
possession by Mar 2028 · Atul Raj Builders Pvt Ltd
Atlantis Residency
possession by Dec 2026 · JK Builders
Atlas Residency A And B
possession by Dec 2028 · Atlas Infratech Pvt.ltd
Atlas Royal B
declared completion Dec 2025 · Atlas Infratech Pvt.ltd
AUM Saheel Tower
declared completion Dec 2023 · Santosh Enterprises
Aura Bliss
possession by Dec 2027 · Aura Monde LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026