MahaRERA Property Intelligence · Mumbai City

ASHISH SEA VIEW

P51900009877 · promoter Sanghvi Gruha Niraman

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51900009877
Registered on22 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sanghvi Gruha Niraman is the promoter of record on 48 projects, of which 8 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
ASHISH SEA VIEW1G+1731 Dec 2020

Complaints & Orders

7 complaints are on the MahaRERA record for this project, with orders passed in 7. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000004413126/06/2018MORRIS PROPERTIES PVT. LTD. vs Nimish Voraorder passed
CC00600000005641903/10/2018KAVYA BUILDCON PVT LTD vs MORRIS PROPERTIES PVT LTDorder passed
CC00600000008965615/06/2019Kamlesh A. Seth duly Constituted attorney of Dr. Pradeep Mehta vs Sanghvi Gruha Nirman Pvt. Ltd.order passed
CC00600000029280324/09/2022SHASHANK MADHUKAR NAGWEKAR vs SANGHVI GRUHA NIRAMAN PVT. LTD.order passed
CC00600000030313731/10/2022Jignesh Vora vs Sanghvi Gruh Nirman Private Limitedorder passed
CC00600000048006416/04/2024Manoj Thakur vs Raoji Shivram Raneorder passed
SM1250004904/04/2025Prabhash Tiwari vs SANGHVI GRUHA NIRAMAN PRIVATE LIMITEDorder passed

Legal & Litigation

The promoter has declared 15 court cases on this project to MahaRERA. 15 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court67152001Pending
City Civil Court47562002Pending
City Civil Court47572002Pending
City Civil Court47582002Pending
High Court24492016Pending
High Court24452016Pending
High Court24482016Pending
High Court24462016Pending
High Court24442016Pending
High Court24432016Pending
High Court24532016Pending
High Court25812016Pending
High Court25792016Pending
High Court24692016Pending
High Court24092016Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Jun 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400025. Per the filed land record, the plot is bounded to the north by 40 FEET WIDE HATISKARWADI MARG, to the south by ICE CREAM FACTORY, to the east by MTNL BUILDING and to the west by AADISH SOCIETY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Bandra Kurla Complex (BKC)7 km
Chhatrapati Shivaji Int'l Airport9 km
Nariman Point / Fort10 km
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Prabhadevi

1515 Moneco
possession by Sep 2026 · Lloyds Realty Developers Limited
25 South Tower A 11th To 47th Floor
possession by Dec 2026 · Twenty Five South Realty Limited
25 South Tower A Upto 10th Floor
possession by Dec 2026 · Twenty Five South Realty Limited
Kalpataru Oceana
possession by Dec 2026 · Kalpataru Properties Pvt. Ltd.
25 South - Central Tower
Deregistered by MahaRERA · possession by Dec 2028 · Twenty Five South Realty Limited
Darshan Inara
possession by Dec 2028 · Darshan Legacy Builders LLP

Major developers building in Prabhadevi

Other RERA-registered projects in Mumbai City

Asteria Heights
declared completion Mar 2022 · Sona Developers
Atharva
declared completion Dec 2025 · Sugee Developers Pvt. Ltd.
Atharva - Samruddhi Residency
declared completion Jun 2022 · Ashwa Realty India PVT LTD
Atlanta Estate Extension
possession by Mar 2028 · Atul Raj Builders Pvt Ltd
Atlantis Residency
possession by Dec 2026 · JK Builders
Atlas Residency A And B
possession by Dec 2028 · Atlas Infratech Pvt.ltd

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026