Bayview Phase-II

E ward, Mazgaon, Mumbai · Kapil Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900048634

Delivery and registration

When is the project declared for completion?

Bayview Phase-II is registered with MahaRERA as P51900048634 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900048634
Registered on10 Jan 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Bayview Phase-II record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kapil Constructions is the promoter of record on 28 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

28projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Bayview Phase-II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+31.

BuildingWingsFloorsDeclared completion
Extended Building No 2 1st to 10th Floor and Building No 2 24th to 30th Floor1G+31-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at E ward, Mazgaon, Mumbai, Mathar Pakhadi Road, Ward E, Mumbai City, 400010. Per the filed land record, the plot is bounded to the north by 3M Wide Lane, to the south by Mathar Pakhadi Road, to the east by Mathar Pakhadi Road and to the west by CTS No - 316 and CTS No - 317. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Nariman Point / Fort5 km
Bandra Kurla Complex (BKC)11 km
Chhatrapati Shivaji Int'l Airport14 km
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kapil Constructions is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Kapil Constructions

Kapil Constructions
FlaggedMumbai City

Other RERA-registered projects in Mazgaon

Harbour Heights
Not filing quarterly progress reports · possession by Dec 2026 · Shree Naman Estate Projects Private Limi
A. M. Residency
possession by Dec 2026 · Alfa Mana Realtors PVT LTD
Shreepati Coronet
possession by Dec 2026 · Shreepati Build Infra Investment Limited
Deja View
possession by Mar 2027 · Zahida ABU Asim Azmi
Piramal Aranya - Wing C
possession by Aug 2027 · Glider Buildcon Realtors Private Limited
Azara Residences
possession by Dec 2027 · Azara Redstone LLP

Major developers building in Mazgaon

Other RERA-registered projects in Mumbai City

Beachcroft
declared completion Jun 2023 · Shree Yashraj Developers
Beaumonte Tower B Phase 1 Sale Building NO 10
declared completion Dec 2024 · Sahana-Sheth
Beaumonte Tower C Sale Bndg NO 10 -Wing C
possession by Dec 2027 · Sahana-Sheth
Belfort BAY – Mumbadevi
possession by Dec 2031 · Shailendra Realtors Pvt. Ltd.
Bellagio
declared completion Mar 2026 · Estelle Estates & Infrastructure Pri
Bellevue Tower - 3
possession by Dec 2027 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026