Bhairaav Blessings

Kalachowky · BHAIRAAV ERECTORS LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900029741

Delivery and registration

When is the project declared for completion?

Bhairaav Blessings is registered with MahaRERA as P51900029741 and the promoter has declared completion for 31 Dec 2022.

31 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900029741
Registered on26 Jun 2021
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Bhairaav Blessings record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Bhairaav Erectors Limited is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Bhairaav Blessings in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
BHAIRAAV BLESSINGS1G+2031 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023Grounds for seeking extension- -Due to certain unprecedented factors including multifold rise in cost of raw material for past two years have posed several challenges in timely pr

Location, Land & Connectivity

Located at Kalachowky, Dattaram lad Marg , Ward ABCD, Mumbai City, 400033. Per the filed land record, the plot is bounded to the north by Western India Mill, to the south by Dattaram Lad Marg, to the east by Mhada Land and to the west by Mhada land. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district1 km
Nariman Point / Fort7 km
Bandra Kurla Complex (BKC)9 km
Chhatrapati Shivaji Int'l Airport12 km
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mazgaon

Pier 33
possession by Sep 2026 · Esque Finmark Private Limited
Atlantis Residency
possession by Dec 2026 · JK Builders
Simana - Wing B - Phase 1
possession by Dec 2026 · Bhoomi Properties
Vardhman Flora Phase I
possession by Dec 2026 · Vardhman Developers LTD
Parshwa Lotus & Rangari Heights
possession by Jan 2027 · Gold Plaza Developers PVT LTD
Darshan Aura
possession by Dec 2028 · Darshan SKY High Constructions LLP

Other RERA-registered projects in Mumbai City

Bhavya Elite
declared completion Jun 2026 · Newlook Constructions Pvt. Ltd
Bhavya Enclave
declared completion Jun 2019 · Bhavya Infrastructures Private Limite
Bhivawani Chawl
possession by Dec 2026 · MS Radhakrishna Developer
Bhoiwada Chandra Bhuvan CHS Ltd
possession by Dec 2026 · Avadhoot Techno Consultant And Engineers
Birla Anayu
possession by Mar 2029 · Birla Estates Private Limited
Birla Niyaara Phase-1
possession by Mar 2028 · Aditya Birla Real Estate Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026