MahaRERA Property Intelligence · Mumbai Suburban

BLUE LOTUS

P51800033826 · KHAR WEST · promoter Rishabraj Estate Developers

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP51800033826
Registered on08 Mar 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rishabraj Estate Developers is the promoter of record on 43 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
BLUE LOTUS1G+1431 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KHAR WEST, JUCTION OF 17TH ROAD AND MAIN AVENUE ROAD, Borivali, Mumbai Suburban, 400052. Per the filed land record, the plot is bounded to the north by BY MAIN AVENUE ROAD, to the south by BY PLOT NO K74, to the east by BY PROPOSED 40FT ROAD and to the west by BY PLOT NO K84. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)4 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district9 km
Powai / Hiranandani business park9 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rishabraj Estate Developers PVT LTD is the promoter on 14 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Rishabraj Estate Developers PVT LTD project & its RERA track record →

Other flagged projects by Rishabraj Estate Developers PVT LTD

Rishabraj Estate Developers PVT LTD
FlaggedMumbai Suburban
Rishabraj Estate Developers PVT LTD
FlaggedMumbai Suburban
Rishabraj Estate Developers PVT LTD
FlaggedMumbai Suburban
Rishabraj Estate Developers PVT LTD
FlaggedMumbai Suburban
Rishabraj Estate Developers PVT LTD
FlaggedMumbai Suburban
Rishabraj Estate Developers PVT LTD
FlaggedMumbai Suburban

Other RERA-registered projects in Khar West

Trishaan
possession by Sep 2026 · Raja Builder
Yogi Sea
possession by Sep 2026 · Yogi Limited
Searock Residences
possession by Oct 2026 · Searock Constructions LLP
259 Park Crest
possession by Dec 2026 · Shree Krishna Homes PVT LTD
33 West
possession by Dec 2026 · Silver Lifespaces Private Limited
Benchmark Plaza
possession by Dec 2026 · Benchmark Projects PVT LTD

Major developers building in Khar West

Other RERA-registered projects in Mumbai Suburban

Blue Sapphire
declared completion Feb 2024 · Blue Canyon Realty PVT LTD
Blue Star Chsl
declared completion Mar 2024 · Thomas Joseph Vazhaparampil
Blue Star Crystal Chsl
possession by Jul 2027 · Paradigm Blue Star LLP
Blue Zone
possession by Mar 2030 · Saptrishi Sunrise Dream House LLP
Bluemoon Annexe
declared completion Dec 2025 · Mudassar Builders & Developers
Blumen
declared completion Dec 2024 · Saur Jagat

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026