Mumbai/Project record

MahaRERA · the public record

Deep Shama

Jambli Naka · N. A Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700023415

Delivery and registration

When is the project declared for completion?

Deep Shama is registered with MahaRERA as P51700023415 and the promoter has declared completion for 30 Dec 2020.

30 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700023415
Registered on12 Dec 2019
Promoter-declared completion30 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Deep Shama record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Deep Shama in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Deep Shama1G+830 Jun 2020

Legal and disputes

What disputes are disclosed?

18 complaints are on the MahaRERA record for Deep Shama, with orders passed in 18 of them.

18complaints

18with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019535123/12/2020Unmesh Prabhakar Athawale vs N. A Developersorder passed
CC00600000019537029/12/2020UNMESH PRABHAKAR ATHAWALE vs N. A Developersorder passed
CC00600000019537929/12/2020POOJA UNMESH ATHAWALE vs N. A Developersorder passed
CC00600000019543529/12/2020POOJA UNMESH ATHAWALE vs N. A Developersorder passed
CC00600000019539630/12/2020ADV SALIL BUTALA vs N A DEVELOPERSorder passed
CC00600000019544129/12/2020PRECILLA N SALDANHA vs N. A Developersorder passed
CC00600000019547001/01/2021PRAMOD D GANDHI vs N. A Developersorder passed
CC00600000019547801/01/2021KALINDI B PATIL vs N. A Developersorder passed
CC00600000019547701/01/2021VIJAY TEMBULKAR vs N. A Developersorder passed
CC00600000019548702/01/2021SUDHIR RAMDAS KOTHARE vs N. A Developersorder passed
CC00600000019549102/01/2021PUSHPA VITHAL AMIN vs N. A Developersorder passed
CC00600000019548602/01/2021VIJAY PARSHURAM PITKAR vs N. A Developersorder passed
CC00600000019552005/01/2021SUSHMA R DHOTARE vs N. A Developersorder passed
CC00600000019552405/01/2021SUSHMA DHOTARE vs N. A Developersorder passed
CC00600000019552605/01/2021ANAND W DESHPANDE vs N. A Developersorder passed
CC00600000019556209/01/2021JIGNA PARESH DESHMUKH vs N. A Developersorder passed
CC00600000019556309/01/2021GANESH R JOSHI vs N. A Developersorder passed
CC00600000019556109/01/2021ARUN MORESHWAR DESHMUKH vs N. A Developersorder passed

Location, Land & Connectivity

Located at Jambli Naka, Dhobi Ali, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by 9 M Wide DP Road, to the south by Survey No 1A 1 2, to the east by Survey No 1A 1 2 and to the west by 9 M wide DP road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Naupada

Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers

Major developers building in Naupada

Other RERA-registered projects in Thane

Deepak Jyoti Heights
declared completion Dec 2021 · Vivaan Constructions
Deepali Residency
declared completion Dec 2022 · Parekh Infraprojects
Deepaswi Heights
possession by Dec 2027 · Yashlata Enterprises
Deepjyoti Chs Ltd
possession by Jun 2028 · Borkar Realty
Deepjyoti Co. Op. Housing Society
possession by Jan 2028 · Aditya Associates
Deepmala CHS LTD
possession by Dec 2027 · S. D. Bhalerao Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026