Mumbai/Project record

MahaRERA · the public record

Gulmohar

Mumbai Suburban · Udyam Enterprises

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005807

Delivery and registration

When is the project declared for completion?

Gulmohar is registered with MahaRERA as P51800005807 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005807
Registered on14 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Gulmohar record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Gulmohar in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Gulmohar1G+7-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Gulmohar, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000004454421/05/2018CHANDRASHEKHAR PRAFULL VAIDYA vs M/S.UDYAM ENTERPRISESorder passed

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400063. Per the filed land record, the plot is bounded to the north by Kulkarni chawl, to the south by Abhpnav shikshan Prasarak Mandal School, to the east by 30ft wide DP Road and to the west by Nandadeep Soc Open plot. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park7 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district19 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon East

Matrusmruti
possession by Oct 2026 · Gio Properties
Samarth Nandadeep Heights
possession by Oct 2026 · Samarth Tsquare
Onyx
possession by Nov 2026 · Shreeram Builders
Goregaon Adwait Chsl - Vijay Sadan
possession by Dec 2026 · Prashant Shirsat
Agarwal Floresta - Maple
possession by Dec 2026 · Homewell Realty LLP
Ashwin Heights
possession by Dec 2026 · Westinrely Developers PVT LTD

Major developers building in Goregaon East

Other RERA-registered projects in Mumbai Suburban

Gulmohur
declared completion Jul 2019 · Sanjay Jumani
Gulraj Paradise
possession by Sep 2026 · M/S Reliable Construction
Gulraj Trinity
declared completion Dec 2025 · M/S Reliable Builders AND Developers
Gumpha Darshan C CO-Operative Housing Society LTD
declared completion Dec 2023 · Samarpan Buildtech LLP
Gundecha Asta Phase I
declared completion May 2018 · Anaya Infrastructure Pvt. Ltd.
Gundecha Desire
declared completion Dec 2019 · Rockline Developers Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026