MahaRERA Property Intelligence · Mumbai Suburban

Gulmohar

P51800005807 · promoter Udyam Enterprises

Certificate SignedDue 30 Jun 2023

Delivery & Registration

MahaRERA registrationP51800005807
Registered on14 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Gulmohar1G+7-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000004454421/05/2018CHANDRASHEKHAR PRAFULL VAIDYA vs M/S.UDYAM ENTERPRISESorder passed

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400063. Per the filed land record, the plot is bounded to the north by Kulkarni chawl, to the south by Abhpnav shikshan Prasarak Mandal School, to the east by 30ft wide DP Road and to the west by Nandadeep Soc Open plot. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park7 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district19 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon East

Matrusmruti
possession by Oct 2026 · Gio Properties
Samarth Nandadeep Heights
possession by Oct 2026 · Samarth Tsquare
Onyx
possession by Nov 2026 · Shreeram Builders
Goregaon Adwait Chsl - Vijay Sadan
possession by Dec 2026 · Prashant Shirsat
Agarwal Floresta - Maple
possession by Dec 2026 · Homewell Realty LLP
Ashwin Heights
possession by Dec 2026 · Westinrely Developers PVT LTD

Major developers building in Goregaon East

Other RERA-registered projects in Mumbai Suburban

Gulmohur
declared completion Jul 2019 · Sanjay Jumani
Gulraj Heights
declared completion Mar 2018 · M/S Neeta Developer
Gulraj Paradise
possession by Sep 2026 · M/S Reliable Construction
Gulraj Trinity
declared completion Dec 2025 · M/S Reliable Builders AND Developers
Gulzar Apartment
declared completion Oct 2020 · Gulzar Ahmed Ainul Haque Shaikh
Gumpha Darshan C CO-Operative Housing Society LTD
declared completion Dec 2023 · Samarpan Buildtech LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026