MahaRERA Property Intelligence · Mumbai City

GURUKRUPA NIGAM

P51900034361 · GHATKOPAR EAST MUMBAI · promoter Gurukrupa Realcon Lifespaces

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP51900034361
Registered on04 Apr 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
GURUKRUPA NIGAM1G+17-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at GHATKOPAR EAST MUMBAI, BLDG NO 78 CTS NO 185 SURVEY NO 236A, Thane, Thane, 400075. Per the filed land record, the plot is bounded to the north by BLDG NO 77, to the south by 9 MTR WIDE ROAD, to the east by BLDG NO 76 and to the west by BLDG NO 80. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Gurukrupa Realcon Lifespaces LLP is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Gurukrupa Realcon Lifespaces LLP

Gurukrupa Realcon Lifespaces LLP
FlaggedMumbai City
Gurukrupa Realcon Lifespaces LLP
FlaggedMumbai City
Gurukrupa Realcon Lifespaces LLP
FlaggedMumbai City
Gurukrupa Realcon Lifespaces LLP
FlaggedMumbai City
Gurukrupa Realcon Lifespaces LLP
FlaggedMumbai Suburban

Other RERA-registered projects in Ghatkopar East

Royal Altezza
possession by Aug 2026 · Shri Ganesh Developers
Mohite Marvel
possession by Sep 2026 · Mohite Realtors LLP
OM Priyadarshani
possession by Sep 2026 · Aakruti Enterprises
Prime Vista
possession by Sep 2026 · Rupvakula Properties Pvt. LTD
THE Legend
possession by Sep 2026 · Empire Maitri Flora Constructions LLP
Damji Shamji Corporate Square - Wing C
possession by Dec 2026 · Coronate Constructions

Major developers building in Ghatkopar East

Other RERA-registered projects in Mumbai City

Gurukrupa Nirmalam
possession by Dec 2026 · Gurukrupa Realcon Infrastructure LLP
Gurukrupa Param
declared completion Dec 2024 · Gurukrupa Realcon Lifespaces LLP
Gurukrupa Satyam
declared completion Mar 2024 · Gurukrupa Realcon Lifespaces LLP
Gurukrupa Vyom
declared completion Nov 2024 · Gurukrupa Realcon Infrabuild LLP
Guruprasad Divine Residency
declared completion Jun 2025 · Rohinton Mehta Builders AND Developers
H And M Royal
declared completion Dec 2025 · Blackplinth Developers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026