Mumbai/Project record

MahaRERA · the public record

Horizon homes

Malad West · HORIZON DREAM HOMES PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Aug 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Aug 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010972

Delivery and registration

When is the project declared for completion?

Horizon homes is registered with MahaRERA as P51800010972 and the promoter has declared completion for 28 Aug 2022.

28 Aug 2022

declared completion

49months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010972
Registered on31 Aug 2017
Promoter-declared completion28 Aug 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Horizon homes record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Horizon Dream Homes is the promoter of record on 42 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

42projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Horizon homes in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Horizon homes1G+15-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Horizon homes, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002316619/02/2018MR. NIRAV LAXMICHAND NANDU and MRS. SEJAL NIRAV NANDU vs DHIREN VINAY CHHEDAorder passed
CC00600000019285504/03/2020NIRAV LAXMICHAND NANDU AND SEJAL NIRAV NANDU vs DHIREN V CHHEDAorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Aug 2020The proposed building under reference is almost completed. However, the Total FSI of 2613.08 sq.m. has been revised and reduced to fully approved FSI of 2374.57 sq.m. Also, some ch
30 Aug 202028 Feb 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 28TH FEB 2022

Location, Land & Connectivity

Located at Malad West, Navy Colony, Borivali, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by Mamletdarwadi main road, to the south by Plot No E of Liberty Garden scheme, to the east by Liberty garden road No 2 and to the west by Liberty garden road No 3. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Horizon Dream Homes Private Limited is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Malad West

Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation
Shreeji Plaza Wing B
possession by Sep 2026 · Siddharth Enterprises
Linkpark
possession by Oct 2026 · Adarsh Industrial Estate Private Limited
Bhagat Grandeur
possession by Dec 2026 · Chirag Agro Fins Private Limited
Liberty Heights
possession by Dec 2026 · VP Casa Constructions LLP
Lovely Chs. LTD
possession by Dec 2026 · Jinam Realtors

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Horizon Nitya
possession by Jun 2028 · Horizon Promoters India LTD
Horizon Tower
possession by Mar 2027 · I.r.developers LLP
Horizon View
possession by Mar 2027 · I.r.developers LLP
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Houston Residency - 15th To 18th Floor
declared completion Apr 2026 · Rare Townships Private Limited
Houston Residency - 19th Floor
declared completion Feb 2026 · Rare Townships Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026