MahaRERA Property Intelligence · Mumbai Suburban

Horizon Nitya

PR1180002500585 · promoter Horizon Promoters India

Certificate SignedDue 25 Jun 2028

Delivery & Registration

MahaRERA registrationPR1180002500585
Registered on14 Aug 2025
Promoter-declared completion25 Jun 2028
Current statusCertificate Signed
Against today23 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Horizon Promoters India is the promoter of record on 40 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~52.5% of the estimated project cost incurred as of the last certificate (₹8.97 Cr spent against a ₹17.09 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 12 homes filed with MahaRERA, 2 are sold/booked and 10 remain available (~17% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹3.16 Cr in agreement value so far. Of that, ₹45.00 Lakh (~14%) is already collected, ₹2.71 Cr receivable — a read on how far along these sales really are. Note: the project registers 24 homes in total, but this sold/unsold inventory filing covers only 12 of them — the other 12 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1102719 sqft (66.82 sqm)₹1.07 Cr
Floor 1103719 sqft (66.82 sqm)₹1.07 Cr
Floor 2202719 sqft (66.82 sqm)₹1.07 Cr
Floor 2203719 sqft (66.82 sqm)₹1.07 Cr
Floor 5503719 sqft (66.82 sqm)₹1.12 Cr
Floor 6602719 sqft (66.82 sqm)₹1.12 Cr
Floor 7702719 sqft (66.82 sqm)₹1.12 Cr
Floor 7703719 sqft (66.82 sqm)₹1.12 Cr
Floor 8802719 sqft (66.82 sqm)₹1.12 Cr
Floor 8803719 sqft (66.82 sqm)₹1.12 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9 and 24 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Mulund Padmavati C.H.S. Ltd.1G+924-

Unit mix on the filing: 24 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Dr, Gajanan Purandhare Road, off Valji Ladha Road, Mulund (West),, Kurla, Mumbai Suburban, 400080. Per the filed land record, the plot is bounded to the north by Plot bearing CTS No. 1364, to the south by Dr. Gajanan Purandare Road, to the east by Plot bearing CTS No. 1317 and to the west by Plot bearing CTS No. 1361. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ14 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Horizon Promoters India LTD is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Horizon Promoters India LTD

Horizon Promoters India LTD
FlaggedMumbai Suburban
Horizon Promoters India LTD
FlaggedMumbai Suburban
Horizon Promoters India LTD
FlaggedMumbai Suburban
Horizon Promoters India LTD
FlaggedMumbai Suburban
Horizon Promoters India LTD
FlaggedMumbai Suburban

Other RERA-registered projects in Mulund West

Kailash Residency
possession by Aug 2026 · Tridev Shreeji Associates
Ananta
possession by Aug 2026 · K Ajmera Developers
AAI Satidevi Paradise
possession by Sep 2026 · Shreenath Developers
Laizer Elegance
Not filing quarterly progress reports · possession by Sep 2026 · Laizer Builders & Developers
THE NEW Anand Deep CHS LTD
possession by Sep 2026 · Shreejee Buildcon
Tirupati Apartments Chsl
possession by Oct 2026 · Tirupati Aparmtnets CO Operative Housing

Major developers building in Mulund West

Other RERA-registered projects in Mumbai Suburban

Horizon Samyak
declared completion Mar 2019 · Horizon Promoters India LTD
Horizon Shloka
declared completion May 2023 · Horizon Promoters India LTD
Horizon Tower
possession by Mar 2027 · I.r.developers LLP
Horizon View
possession by Mar 2027 · I.r.developers LLP
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Houston Residency - 15th To 18th Floor
declared completion Apr 2026 · Rare Townships Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026