Kashish Park Ghatkopar

P51800002692 · Ghatkopar East · promoter Ladam Homes Pvt

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51800002692
Registered on02 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
Centroid1G+1631 Dec 2020

Complaints & Orders

9 complaints are on the MahaRERA record for this project, with orders passed in 9. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000002317920/02/2018SHANKAR B AUSARIKAR vs SUMESH AGARWALorder passed
CC00600000005506530/07/2018Ladam Homes Pvt. Ltd. vs Shankar Auserikarorder passed
CC00600000005581520/08/2018DNYANESHWAR LAXAMAN MORE vs LADAM HOMES PVT LTDorder passed
CC00600000005763331/08/2019TUSHAR SHANKAR HULE vs LADAM HOMES PRIVATE LIMITED (FORMERLY KNOWN AS LADAM HOMES LIMITED)order passed
CC00600000007939221/05/2019Rajesh Panigrahi vs Ladam Homes Ltd (Sumesh Agarwal)order passed
CC00600000014103727/09/2019SOJAL AMIT SAWANT AND AMIT NAMDEO SAWANT vs LADAM HOMES PRIVATE LIMITED (FORMERLY KNOWN AS LADAM HOMES LIMITED)order passed
CC00600000016136802/11/2019Prakash Jagannath Hinge & Sheetal P. Hinge vs Ladam Homes Private Limitedorder passed
CC00600000019644922/03/2021Aditya Dnyaneshwar Shete vs Ladam Homes Pvt. Ltd.order passed
CC00600000019501412/12/2020Harshada Bhalesh Naik vs Ladam Homes Pvt Ltdorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Small Cause CourtMARJI/96/20172016Hearing

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Jun 2022OC is held up for want of Compliance of matters which involves the Government Authorities and further actions at their end but their functioing has been disrupted for last one year

Location, Land & Connectivity

Located at Ghatkopar East, Rajaram Bane Marg, Thane, Thane, 400075. Per the filed land record, the plot is bounded to the north by 6 mtr wide Road, to the south by Plot of Rehab Buildings of Laxminagar Mauli CHS, to the east by Plot of land bearing CTS no 223 of Savli CHS and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)6 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district14 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Royal Altezza
possession by Aug 2026 · Shri Ganesh Developers
Mohite Marvel
possession by Sep 2026 · Mohite Realtors LLP
OM Priyadarshani
possession by Sep 2026 · Aakruti Enterprises
Prime Vista
possession by Sep 2026 · Rupvakula Properties Pvt. LTD
THE Legend
possession by Sep 2026 · Empire Maitri Flora Constructions LLP
Damji Shamji Corporate Square - Wing C
possession by Dec 2026 · Coronate Constructions

Major developers building in Ghatkopar East

Other RERA-registered projects in Mumbai Suburban

Kashmiri Heights
declared completion Jun 2022 · M.k.enterprises
Kasturi Milan
declared completion Feb 2025 · H Rishabraj Realty
Kateeleshwari Apartment
declared completion Dec 2021 · Kateeleshwari Developers Private Limited
Kateeleshwari Arcade
possession by Dec 2027 · Kateeleshwari Developers PVT LTD AND Ram
Katha
declared completion Dec 2019 · Tanvi Constructions
Kaustubh Capital
possession by Sep 2030 · Kaustubh Construction Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026