KRYPTON TWIN TOWER BUILDING B WING II

P51900003096 · promoter Krypton Construction Private

Certificate SignedDue 30 Apr 2019

Delivery & Registration

MahaRERA registrationP51900003096
Registered on04 Aug 2017
Promoter-declared completion30 Apr 2019
Current statusCertificate Signed
Against todayabout 87 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Krypton Construction Private is the promoter of record on 4 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+28.

BuildingWingsFloorsDeclared completion
BUILDING B WING II1G+28-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court3692017Disposed
Bombay High Court34082016Pending
Bombay High Court30342017Withdrawn

Location, Land & Connectivity

Located at Ward ABCD, Mumbai City, 400015. Per the filed land record, the plot is bounded to the north by BALMER LAURIE CO LTD, to the south by JHAKARIA BUNDER ROAD, to the east by PROPERTY BEARING C S NO 168 and to the west by JHAKARIA BUNDER ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~103 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park103 km
Baner–Balewadi belt109 km
Pune Junction / city centre119 km
Pune Int'l Airport (Lohegaon)121 km
Kharadi / EON IT Park125 km
Magarpatta / Hadapsar IT125 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sewri

Avenue 15
possession by Sep 2026 · Ramesh Barrel Supplying Co
J K Apartment
possession by Dec 2026 · Plus Properties PVT LTD
The Gateway
possession by Sep 2028 · LH Residential Housing Private Limited
Aqua BAY
possession by Dec 2028 · Chamunda Infrastructure Limited
The Royal Oaks Residency
possession by Dec 2030 · Mighty Oaks Constructions LLP
Lodha Sewri Project
possession by Dec 2032 · Lodha Developers Limited

Major developers building in Sewri

Other RERA-registered projects in Mumbai City

KSA Amaira
possession by Dec 2029 · K S A AND Associates
KSA Elaf
declared completion Jun 2023 · Shezad Abdul Aziz Reshamwala
KSA Grande
declared completion Jun 2023 · M/s.faber Constructions
KSA Imperia
possession by Dec 2030 · KSA Enterprises
KSA Palms
possession by Dec 2027 · M/s. KSA Enterprises
KSA Pride
declared completion Jun 2023 · KSA AND Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026