MahaRERA Property Intelligence · Mumbai City

Lodha Sewri Project

PR1170002502863 · Sewree · promoter Lodha

Certificate SignedDue 31 Dec 2032

Delivery & Registration

MahaRERA registrationPR1170002502863
Registered on16 Mar 2026
Promoter-declared completion31 Dec 2032
Current statusCertificate Signed
Against today77 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Sales & Inventory

Of 354 homes filed with MahaRERA, 0 are sold/booked and 354 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+60 and 354 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SALE BUILDING NO. 1:- Wing A1G+56253-
SALE BUILDING NO. 1:- Wing B1G+60101-

Unit mix on the filing: 351 residential and 3 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Sewree, Parel- Sewree Division at T.J Road, Mumbai City, Mumbai City, 400015. Per the filed land record, the plot is bounded to the north by CS No. 1B/167, to the south by CS No. 9/172 & Proposed 18.30 Mtrs DP Road, to the east by Proposed 18.30 Mtrs DP Road and to the west by CS NO. 211. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Bandra Kurla Complex (BKC)8 km
Nariman Point / Fort8 km
Chhatrapati Shivaji Int'l Airport11 km
Powai / Hiranandani business park15 km
Andheri MIDC / SEEPZ15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 133 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedMumbai Suburban
Lodha Developers Limited
FlaggedMumbai Suburban
Lodha Developers Limited
FlaggedMumbai Suburban
Lodha Developers Limited
FlaggedRaigarh
Lodha Developers Limited
FlaggedRaigarh
Lodha Developers Limited
FlaggedRaigarh

Other RERA-registered projects in Sewri

Avenue 15
possession by Sep 2026 · Ramesh Barrel Supplying Co
J K Apartment
possession by Dec 2026 · Plus Properties PVT LTD
The Gateway
possession by Sep 2028 · LH Residential Housing Private Limited
Aqua BAY
possession by Dec 2028 · Chamunda Infrastructure Limited
The Royal Oaks Residency
possession by Dec 2030 · Mighty Oaks Constructions LLP
Sobha Inizio
possession by Mar 2034 · Sobha Limited

Major developers building in Sewri

Other RERA-registered projects in Mumbai City

Lodha Signet Lower Parel Wing A
declared completion May 2025 · Lodha Developers Limited
Lodha Signet Lower Parel Wing B
possession by Aug 2026 · Lodha Developers Limited
Lodha Venezia - 49th TO 65th Floor
declared completion Dec 2018 · Lodha Developers Limited
Lodha Venezia- Wing C
declared completion Dec 2023 · Lodha Developers Limited
Lodha Worli Residential Project
possession by Jun 2033 · Lodha Developers Limited
Lotus
possession by Feb 2030 · Shreem Reality

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026