Mumbai/Project record

MahaRERA · the public record

KSA Royale B Wing

Byculla · KSA Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2029declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900079454

Delivery and registration

When is the project declared for completion?

KSA Royale B Wing is registered with MahaRERA as P51900079454 and the promoter has declared completion for 31 Dec 2029.

31 Dec 2029

declared completion

39months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900079454
Registered on06 Mar 2025
Promoter-declared completion31 Dec 2029
Current statusCertificate Signed
Against today39 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KSA Royale B Wing record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KSA Royale B Wing in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
B Wing1G+21-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Byculla, 1st & 2nd Cross Lane & Sankli Street , Ward E, Mumbai City, 400008. Per the filed land record, the plot is bounded to the north by Public Road, to the south by Property of Haji A H Rehmatulla, to the east by Property of Municipality and to the west by Property of Fatemabai Mohd Ally Thungekar. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Byculla

Kings Tower
possession by Sep 2026 · Mohammed Eshaq ALI Vadgama
Shelaji Avenues
possession by Dec 2026 · Ashirwad Shelaji Developers LLP
Baug E Umar
possession by Dec 2026 · Mahanagar Constructions Private Limited
Golden Residency
possession by Dec 2026 · Golden Realty
Nemat -E- Farooque Heritage
possession by Dec 2026 · Falakdeveloper
White Flower Residency
possession by Dec 2026 · White Flowers Realty LLP

Major developers building in Byculla

Other RERA-registered projects in Mumbai City

KSA Square
possession by Dec 2028 · Faber Constructions
Kshitij Omkar
possession by Nov 2030 · Omkar CHS Ltd
KUL Elegance
declared completion Dec 2024 · Kumar Urban Development Private Limited
La Belleza
possession by Oct 2028 · Qaswa Enterprises
La Mer Residences
possession by Dec 2027 · Excellent Realtor Developers
La Verna
declared completion Dec 2019 · M/s Qaswa Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026