MahaRERA Property Intelligence · Mumbai Suburban

MALAD WEBB

P51800052532 · MALAD WEST · promoter Nee-Raa Enterprises

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP51800052532
Registered on08 Sep 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~20.0% of the estimated project cost incurred as of the last certificate (₹91.46 Lakh spent against a ₹4.57 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3 and 12 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Malad Webb1G+31230 Jun 2025

Unit mix on the filing: 12 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202530 Jun 2026Due to shortage of Funds at that time project could not be completed
30 Jun 202531 Dec 2027due to unforeseen statutory approvals and certain construction related challenges .

Location, Land & Connectivity

Located at MALAD WEST, 19/1, BRAHMAN SABHA ROAD, Borivali, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by CTS NO 762-B, to the south by CTS NO 786 OR 756, to the east by CTS NO 761 MORESHWER K JOSHI and to the west by BRAHMAN SHABHA ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad West

Ajmera Arham
possession by Jul 2026 · Vishal Construction
Imperial Hava Hira
possession by Jul 2026 · Shree SAI Realty
Liberte64
possession by Aug 2026 · Jadhwani Infrastructure LLP
Ramdev Veeral Heights
possession by Aug 2026 · Ramdev Associates
Rajgopal Building
possession by Sep 2026 · Harmony AND Prosperity Developer
Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Malhar Guide
declared completion Dec 2024 · Atlanta Group
Malhar Krishna
possession by Dec 2026 · Mulund Krishna Niwas Chsl
Malhar Malti
possession by Mar 2027 · Atlanta Developers
Malwani Asha Jeevan CHS LTD
declared completion Mar 2018 · Malwani Asha Jeevan CHS LTD
Malwani Sea View CHS LTD
declared completion Mar 2018 · Malwani Sea View CHS LTD
Malwani West View CHS LTD
declared completion Mar 2018 · Malwani West View CHS LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026