Marvel Gold - Phase II - COLLOSEUM

P51800016143 · HARIJAN COLONY VALMIKI NAGAR · promoter Swaroop Constructions Private

Certificate SignedDue 31 Oct 2024

Delivery & Registration

MahaRERA registrationP51800016143
Registered on17 Apr 2018
Promoter-declared completion31 Oct 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Swaroop Constructions Private is the promoter of record on 25 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
Colloseum1G+2231 Dec 2021

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000040823624/11/2023Purushothaman Pillai vs Swaroop Constructions Private Limited and Vasant Developersorder passed
CC00600000040862328/12/2023Swati Avadhoot Tambe vs Jayshil Bhimani, Ketan Bhalodiya, Muljibhai Bhimaniorder passed
CC1240048921/10/2024VISHWAS SAHADEO DALVI vs Swaroop Constructions Private Limitedorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202231 Oct 2024We have completed 80% construction of the building but due to shortage of labour and materials there has been delay in the completion of the construction of the building. We would
30 Dec 202201 Dec 2023We had received our first CC in April 2019, however due to the pandemic the was stuck for a while, then when the situation got better and things were reopening, we had to face seve

Location, Land & Connectivity

Located at HARIJAN COLONY VALMIKI NAGAR, TANK ROAD, CTSO Goregaon, Mumbai Suburban, 400078. Per the filed land record, the plot is bounded to the north by CTS 413, to the south by CTS 406, to the east by CTS 554 555 and to the west by CTS 411. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Swaroop Constructions Private Limited is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Swaroop Constructions Private Limited

Swaroop Constructions Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Bhandup West

Shraddha Evoque
possession by Aug 2026 · Shraddha Landmark Private Limited
Primo
possession by Sep 2026 · Ceear Land Developers LLP
Aureate
possession by Dec 2026 · Beauty Ganraj Construction LLP
Fairmont
possession by Dec 2026 · Trident Ozone LLP
Neptune Eleve Wing A
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing B
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private

Major developers building in Bhandup West

Other RERA-registered projects in Mumbai Suburban

Marvel Pride
possession by Oct 2027 · Marvellous Builders Private Limited
Mary Villa
declared completion Dec 2023 · H&d Projects
Mascarenhas Apartment
possession by Dec 2026 · SAI Universal Realtors & Developers
Mass Eminence
possession by Dec 2026 · Mass Estate Development Corporation
Mass Ionics
declared completion Jun 2026 · Mass Buildsquare Structure Private Limit
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.