MahaRERA Property Intelligence · Palghar

Mittal Enclave Gokul Sector Bldg No 4

P99000006573 · promoter Sealink Construction Co

Certificate SignedDue 30 Oct 2020

Delivery & Registration

MahaRERA registrationP99000006573
Registered on14 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sealink Construction Co is the promoter of record on 6 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Gokul Sector Bldg No 4 Wing A B C D1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Oct 202030 Apr 2020VVCMC has put the grant of OC on hold owing to the issues relating to wet-lands in Vasai/Virar region, and the matter is still under consideration of VVCMC/ Government of Maharasht

Location, Land & Connectivity

Located at Ward ABCD, Mumbai City, 401208. Per the filed land record, the plot is bounded to the north by Road, to the south by Building no 2, to the east by Open Plot and to the west by Garden. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ26 km
Powai / Hiranandani business park28 km
Chhatrapati Shivaji Int'l Airport30 km
Bandra Kurla Complex (BKC)33 km
Lower Parel / Worli business district40 km
Nariman Point / Fort48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sealink Construction Co. Pvt. Ltd. is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Sealink Construction Co. Pvt. Ltd.

Sealink Construction Co. Pvt. Ltd.
FlaggedPalghar
Sealink Construction Co. Pvt. Ltd.
FlaggedPalghar
Sealink Construction Co. Pvt. Ltd.
FlaggedPalghar
Sealink Construction Co. Pvt. Ltd.
FlaggedPalghar

Other RERA-registered projects in Vasai East

Samruddhi Ind. Estate
possession by Jul 2026 · Krisha Buildtech LLP
Armaan Crystal Uptown
possession by Aug 2026 · Armaan Housing LLP
Nakshatra Aarambh
possession by Sep 2026 · JSB Shelters LLP
AAI Chandika Hills
possession by Sep 2026 · Shivam Builders & Developers
Dreams Heights Building NO- I
possession by Sep 2026 · Lodha Builders AND Developers
Trinity Oasis
possession by Sep 2026 · Harsh Tirupati Developers LLP

Major developers building in Vasai East

Other RERA-registered projects in Palghar

Mittal Enclave Mittal Centre Shopping B-1
declared completion Dec 2018 · Sealink Construction Co. Pvt. Ltd.
Mittal Enclave Mittal Centre Shopping B-3
declared completion Dec 2018 · Sealink Construction Co. Pvt. Ltd.
MJV Corporation
possession by Jun 2027 · MJV Corporation
MK Proud
possession by Dec 2030 · MK Group
Mldc Yashwant Orchid Phase I
possession by Dec 2030 · SAI Rydam Realtors PVT LTD
Mldc Yashwant Orchid Phase II
possession by Dec 2029 · SAI Rydam Realtors PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026