MahaRERA Property Intelligence · Mumbai City

MONT KIARA

P51900002127 · promoter Tanishq Builders

Certificate SignedDue 30 Sep 2020

Delivery & Registration

MahaRERA registrationP51900002127
Registered on31 Jul 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tanishq Builders is the promoter of record on 9 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
MONT KIARA1G+20-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000008991230/06/2019DR PRAVINCHANDRA SONONE vs AMAR CHHEDAorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202030 Mar 2020The delay is due to late delivery of Elevators from Mitsubushi Elevators India Pvt Ltd. The delivery is expected to be received sometime in may 2019. The lift is going to Imported

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400019. Per the filed land record, the plot is bounded to the north by 287, to the south by DEODHAR ROAD, to the east by SIR BHALCHANDRA ROAD and to the west by 273. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Lower Parel / Worli business district4 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ12 km
Nariman Point / Fort12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tanishq Builders is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Tanishq Builders

Tanishq Builders
FlaggedMumbai Suburban
Tanishq Builders
FlaggedMumbai Suburban

Other RERA-registered projects in Matunga

Balkrishna Hills
possession by Sep 2026 · Oriental Contractors Private Limited
Gulraj Paradise
possession by Sep 2026 · M/S Reliable Construction
Signare
Past its declared completion date · possession by Sep 2026 · Tejukaya Buildcon
Chhaya
possession by Dec 2026 · Fortune Realty
Jade Acharya
possession by Dec 2026 · Raghavendra Acharya & Others
Shayona
possession by Dec 2026 · Devesh Narendra Jani

Major developers building in Matunga

Other RERA-registered projects in Mumbai City

Montesouth-1
declared completion Dec 2022 · Swayam Realtors & Traders LLP
Montesouth-2
declared completion Dec 2023 · Swayam Realtors & Traders LLP
Montesouth-3
declared completion Jun 2024 · Swayam Realtors & Traders LLP
Montesouth-4
declared completion Jun 2025 · Swayam Realtors & Traders LLP
Montesouth-5
declared completion Dec 2025 · Swayam Realtors & Traders LLP
Montesouth-6
declared completion Jun 2026 · Swayam Realtors & Traders LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026