N SQUARE

P51800009863 · promoter Parthesh Developers Private

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51800009863
Registered on22 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Parthesh Developers Private is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
N SQUARE1G+18-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000007922017/05/2019Inderji Bhatia vs Parthesh Developers pvt ltdorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Dec 2020Inadvertent Delay is caused due to Stop Work Notice which came to be issued by MCGM for Mistake/Fraud committed by the erstwhile Architect/L.S.. The Construction of Building Projec
30 Dec 202230 Jun 2022The construction of the project is completed. we are / were in the process of making applications for obtaining the Building Completion and Full Occupation Certificate for the said

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400052. Per the filed land record, the plot is bounded to the north by F 117, to the south by F 119, to the east by 24th ROAD and to the west by F 108. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport4 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district8 km
Powai / Hiranandani business park9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khar West

Trishaan
possession by Sep 2026 · Raja Builder
Yogi Sea
possession by Sep 2026 · Yogi Limited
Searock Residences
possession by Oct 2026 · Searock Constructions LLP
259 Park Crest
possession by Dec 2026 · Shree Krishna Homes PVT LTD
33 West
possession by Dec 2026 · Silver Lifespaces Private Limited
Benchmark Plaza
possession by Dec 2026 · Benchmark Projects PVT LTD

Major developers building in Khar West

Other RERA-registered projects in Mumbai Suburban

N.v. Deshmukh - Neptune Gulmohar
declared completion Dec 2019 · Vedant Realtors LLP
Nageshwar SRA CHS
possession by Dec 2026 · Vishwambhar Constructions
Nahar Cayenne
declared completion Feb 2018 · Nahar Builders LTD
Nahars Chandi Valley - Phase I
possession by Dec 2030 · Nahar Builders Limited
Nahid Heights
possession by Dec 2026 · M/S Nahid Enterprises
Nahur Gaonthan Shiv Shakti CHS LTD
declared completion Jun 2025 · OM Builders AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026