Mumbai/Project record

MahaRERA · the public record

No. O 58

Majiwade · T Bhimjyani Realty Pvt.Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700020741

Delivery and registration

When is the project declared for completion?

No. O 58 is registered with MahaRERA as P51700020741 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700020741
Registered on08 May 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for No. O 58 record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Bhimjyani Realty is the promoter of record on 11 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

11projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for No. O 58 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
O 581G+231 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High CourtCARBP/752017Conciliation Mediation Agreement Has Been Executed To Settle Outstanding Disputes Between The Partie
Bombay High CourtCP/4012016Conciliation Mediation Agreement Has Been Executed To Settle Outstanding Disputes Between The Partie
Supreme Court Of IndiaSC/50992016Conciliation Mediation Agreement Has Been Executed To Settle Outstanding Disputes Between The Partie

Location, Land & Connectivity

Located at Majiwade, Mullabaug, Kurla, Mumbai Suburban, 400610. Per the filed land record, the plot is bounded to the north by Building N 51, to the south by 6 M Wide Internal Road, to the east by Proposed Tower B 117 S No 318 Part and to the west by Building L 57. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

T Bhimjyani Realty Pvt.ltd. is the promoter on 10 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every T Bhimjyani Realty Pvt.ltd. project & its RERA track record →

Other flagged projects by T Bhimjyani Realty Pvt.ltd.

T Bhimjyani Realty Pvt.ltd.
FlaggedThane
T Bhimjyani Realty Pvt.ltd.
FlaggedThane
T Bhimjyani Realty Pvt.ltd.
Past its declared completion dateThane
T Bhimjyani Realty Pvt.ltd.
FlaggedThane
T Bhimjyani Realty Pvt.ltd.
FlaggedThane

Other RERA-registered projects in Majiwade

Infinity Towers
possession by Dec 2026 · T Bhimjyani Realty Pvt.ltd.
Raunak Imperial
possession by Dec 2026 · Raunak Avenue Realty
ZEN
possession by Dec 2026 · Neelkanth Realtors PVT LTD
Serein Phase II
possession by May 2027 · Ardent Properties Private Limited
Mahavir Spring -Daffodils-P3
possession by Dec 2027 · Vinayak Developers
Courtyard - Asteria A
possession by Dec 2027 · Courtyard Real Estate Private Limited

Major developers building in Majiwade

Other RERA-registered projects in Thane

Noble SKY
possession by Dec 2033 · Paradise MKH Builders & Developers
Noor Residency
declared completion Jun 2025 · Al Araaf Infra Private Limited
North Barcelona Wing D
declared completion Jun 2026 · JP Infra Residency Private Limited
North Imperial Greens - Tower 1
possession by Dec 2032 · Skylark Buildspace Private Limited
North Imperial Greens -Tower 2
possession by Dec 2031 · Skylark Buildspace Private Limited
North Westend Tower 1
possession by Dec 2029 · JP Infra Realty Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026