MahaRERA Property Intelligence · Mumbai Suburban

OM PALACE

P51800002838 · MALAD WEST · promoter Enterprises

Certificate SignedDue 31 Jul 2023

Delivery & Registration

MahaRERA registrationP51800002838
Registered on04 Aug 2017
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27.

BuildingWingsFloorsDeclared completion
OM PALACE1G+2230 Jun 2019
SNEHAL SADAN SRA CHSL1G+2730 Jun 2019

Complaints & Orders

8 complaints are on the MahaRERA record for this project, with orders passed in 8. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000001251921/12/2017girish chopra vs p g enterprisesorder passed
CC00600000001253221/12/2017umma tekchandani vs p g enterprisesorder passed
CC00600000004451816/05/2018Nimesh Pandya vs Mukesh Makwanaorder passed
CC00600000005659916/10/2018SMT.KAILASHGOURI G PUROHIT & MR.PRAGNESH G PUROHIT vs BHAVESH.N.SHAHorder passed
CC00600000007945209/06/2019Ms. Mekhola Ganguly vs Makwana Grouporder passed
CC00600000019610122/02/2021Mekhola Ganguly vs P. G. Enterprisesorder passed
CC00600000019516506/12/2020Snehal Sadan Sale vs Makwana / P Gorder passed
CC00600000020961704/01/2022Mr Suresh R Shettyar and Mrs Surya S Shettyar vs P G Enterprisesorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court Dindoshi12662016Chamber Summons On Behalf Of The Slum Society Admitted

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Jul 202331 Jul 2023We are hereby explaining the delay in completion the project on time. The primary reasons of delay was non availability of the Staff due to COVID-19 pandemic and delay in obtaining
31 Jul 202329 Jun 2020Declaration We are hereby explaining the delay in completion of the project on time. The primary reason of delay was obtaining approvals ontime for the Rehab Building and Sale B

Location, Land & Connectivity

Located at MALAD WEST, MITTAL COLLEGE ROAD, Borivali, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by CTS NO - 346, to the south by CTS NO - 340, to the east by CTS NO - 349 AND 350 and to the west by CTS NO - 328. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad West

Ajmera Arham
possession by Jul 2026 · Vishal Construction
Imperial Hava Hira
possession by Jul 2026 · Shree SAI Realty
Liberte64
possession by Aug 2026 · Jadhwani Infrastructure LLP
Ramdev Veeral Heights
possession by Aug 2026 · Ramdev Associates
Rajgopal Building
possession by Sep 2026 · Harmony AND Prosperity Developer
Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

OM Palace
declared completion Jan 2018 · Madhusudan Sitaram Junnarkar
OM Palace
possession by Aug 2027 · Umiya Builders
OM Paras
possession by Apr 2027 · OM Arch Realty LLP
OM Priyadarshani
possession by Sep 2026 · Aakruti Enterprises
OM Raja
declared completion Sep 2025 · Sainath Corporation
OM Residency
declared completion Jun 2023 · Oscar Infrastructure Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026