MahaRERA Property Intelligence · Pune

OM SAHIL SOLITAIRE

P51900010839 · promoter Om Sahil Solitaire

Certificate SignedDue 21 Sep 2023

Delivery & Registration

MahaRERA registrationP51900010839
Registered on31 Aug 2017
Promoter-declared completion21 Sep 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Om Sahil Solitaire is the promoter of record on 12 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+32.

BuildingWingsFloorsDeclared completion
BLDG NO 1 REHAB1G+14-
BLDG NO 2 MCGM1G+23-
BLDG NO 31G+8-
BLDG NO 4 SALE1G+3220 Sep 2023
BLDG NO 51G+31-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court952014Pending

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400015. Per the filed land record, the plot is bounded to the north by NEW SEWREE LABOUR CAMP, to the south by SHIVAJI NAGAR, to the east by RAFI AHMED KIDWAI ROAD and to the west by SEWREE CEMETRY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~103 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park103 km
Baner–Balewadi belt109 km
Pune Junction / city centre119 km
Pune Int'l Airport (Lohegaon)121 km
Kharadi / EON IT Park124 km
Magarpatta / Hadapsar IT125 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sewri

Avenue 15
possession by Sep 2026 · Ramesh Barrel Supplying Co
J K Apartment
possession by Dec 2026 · Plus Properties PVT LTD
The Gateway
possession by Sep 2028 · LH Residential Housing Private Limited
Aqua BAY
possession by Dec 2028 · Chamunda Infrastructure Limited
The Royal Oaks Residency
possession by Dec 2030 · Mighty Oaks Constructions LLP
Lodha Sewri Project
possession by Dec 2032 · Lodha Developers Limited

Major developers building in Sewri

Other RERA-registered projects in Mumbai City

OM SAI SRA CHS LTD
declared completion Dec 2025 · Riddhi Siddhi Developers
Om Sat
declared completion Dec 2019 · Shree Siddhi Developers
OM Shiv Shankar CHS
declared completion Feb 2021 · Govind Marutirao Kakde
OM Shree Janabai
possession by Dec 2026 · Signet Properties Private Limited
OM Siddhi SRA CHS LTD
declared completion Dec 2025 · M/s. OM Siddhi Venture
OM Swami Anand
declared completion Dec 2017 · Aanandvardhan Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026