MahaRERA · the public record
PENTAGON HEIGHTS
Bhiwandi · DAMJI HARI CONSTRUCTIONS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
29 Nov 2019
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700010871
Delivery and registration
When is the project declared for completion?
PENTAGON HEIGHTS is registered with MahaRERA as P51700010871 and the promoter has declared completion for 29 Nov 2019.
29 Nov 2019
declared completion
82months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700010871 |
| Registered on | 31 Aug 2017 |
| Promoter-declared completion | 29 Nov 2019 |
| Current status | Certificate Signed |
| Against today | about 82 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PENTAGON HEIGHTS record 10 quarterly progress reports since registration.
10quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Damji Hari Constructions is the promoter of record on 17 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
17projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for PENTAGON HEIGHTS in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| PENTA 1 - BUILDING A | 1 | G+8 | 12 Oct 2017 |
| PENTA 3 - BUILDING B | 1 | G+15 | 28 Mar 2019 |
Legal and disputes
What disputes are disclosed?
6 complaints are on the MahaRERA record for PENTAGON HEIGHTS, with orders passed in 6 of them.
6complaints
6with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000012194 | 25/12/2017 | Zaheed Shamsuddin Shaikh & 3 Others vs Paresh Bhanushali & Other Promoters | order passed |
| CC006000000023305 | 12/09/2018 | ansari sharif saleem vs DAMJI HARI CONSTRACTION | order passed |
| CC006000000023163 | 31/01/2018 | Afroze Amanulla Khalipha vs DAMJI HARI CONSTRUCTIONS | order passed |
| CC006000000044491 | 12/05/2018 | DAMJI HARI CONSTRUCTIONS vs Mohammed Shafiq Ayub Ansari | order passed |
| CC006000000056213 | 15/09/2018 | Abdul Hamid Abdul Latif Shaikh vs M/S DAMJI HARI CONSTRUCTION | order passed |
| CC006000000198693 | 16/10/2021 | VASI AHMAD MOMIN AND NUSRAT JAHAN VASI AHMAD MOMIN vs M/S. DAMJI HARI CONSTRUCTIONS | order passed |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 29 Nov 2019 | WE HAD APPLIED FOR OCCUPATION CERTIFICATE FOR BUILDING B (PENTA-3) DATED 15.11.2018. WE ARE EXPECTING THE SAME APPROVAL BEFORE OUR PROPOSED EXTENDED DATE OF COMPLETION. WE HAD REC |
Location, Land & Connectivity
Located at Bhiwandi, Andheri, Mumbai Suburban, 421302. Per the filed land record, the plot is bounded to the north by ADJOINING SURVEY NO 92, to the south by ADJOINING SURVEY NO 72-4, to the east by ADJOINING SURVEY NO 72-3 AND 72-4 and to the west by ADJOINING SURVEY NO 95. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 28 km |
| Andheri MIDC / SEEPZ | 29 km |
| Chhatrapati Shivaji Int'l Airport | 33 km |
| Bandra Kurla Complex (BKC) | 35 km |
| Lower Parel / Worli business district | 43 km |
| Nariman Point / Fort | 50 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.