MahaRERA Property Intelligence · Thane
P51700011742 · Ambarnath · promoter Sai Ashray Developers
| MahaRERA registration | P51700011742 |
| Registered on | 31 Aug 2017 |
| Promoter-declared completion | 17 Jul 2023 |
| Current status | Certificate Signed |
| Against today | about 36 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Sai Ashray Developers is the promoter of record on 23 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| PRASADAM WING JKM | 1 | G+8 | 17 Jul 2021 |
21 complaints are on the MahaRERA record for this project, with orders passed in 20. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000000375 | 04/09/2017 | SANJAY K. SONI vs Sai Ashray Developers Private Limited | order passed |
| CC006000000000402 | 05/09/2017 | RAJESH SONI vs M/s. Sai Ashray Developers Private Limited | order passed |
| CC006000000058123 | 17/02/2019 | RAJESH K. SONI vs M/s. Sai Ashray Developers | order passed |
| CC006000000056527 | 11/10/2018 | ASHOK RAGHAVAN vs Sai Ashray Developers Pvt Ltd | order passed |
| CC006000000194674 | 27/10/2020 | ASHOK RAGHAVAN vs M/s SAI ASHRAY DEVELOPERS PVT LTD | order passed |
| CC006000000195051 | 30/11/2020 | SANDEEP SHENOY K vs SAI ASHRAY DEVELOPERS PVT. LTD. | order passed |
| CC006000000044389 | 02/05/2018 | MAHENDRA PRATAP SINGH vs Sai Ashray Developers Private Limited | order passed |
| CC006000000078996 | 02/05/2019 | Hindeshwar Narayan Singh vs Sai Ashray Developers Pvt. Ltd. | order passed |
| CC006000000197767 | 27/07/2021 | MR. SAMEER GOVING DALVI vs M/S SAI ASHRAY DEVELOPERS PVT. LTD. | order passed |
| CC006000000192801 | 05/03/2020 | SEEMA K MORE vs JAGDISH BHAGWANDAS AHUJA | order passed |
| CC006000000195140 | 05/12/2020 | Kusaraju chikkale vs Sai ashray developer pvt ltd/ahuja hive prasadam | order passed |
| CC006000000196737 | 29/07/2021 | Dashrath Bacchav Walunj vs Sai Ashray Developers Pvt Ltd. | order passed |
| CC006000000210105 | 23/02/2022 | T V PADMAKUMAR MENON vs M/S SAI ASHRAY DEVELOPERS PRIVATE LIMITED | order passed |
| CC006000000251355 | 04/06/2022 | SATISH GOKULDAS SHIVTARKAR vs SAI ASHRAY DEVELOPERS PVT. LTD. | order passed |
| CC006000000395881 | 20/05/2023 | Ashok Nagpal vs Sai Ashray Developers Pvt. Ltd. | order passed |
| CC006000000490390 | 06/05/2024 | Kanchan Nagpal vs Sai Ashray Developers Pvt Ltd | order passed |
| CC006000000490392 | 06/05/2024 | Ashok Nagpal vs Sai Ashray Developers | order passed |
| CC12400354 | 06/10/2024 | Shirish Ulhas Mundhe vs SAI ASHRAY DEVELOPERS PVT LTD | order passed |
| CC12400560 | 25/10/2024 | DEEPAK BHAJANLAL DUSEJA vs SAI ASHRAY DEVELOPERS PVT LTD | order passed |
| CC12503936 | 09/11/2025 | Hindeshwar Narayan Singh vs SAI ASHRAY DEVELOPERS PVT LTD | order passed |
| CC12604340 | 11/07/2026 | Anand Ramchandra Reddy vs SAI ASHRAY DEVELOPERS PVT LTD | pending / no order on file |
The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Civil Court Ulhasnagar | 371 | 2015 | Pending |
| State Consumer Dispute Redressal Commission | 393 | 2018 | Pending |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 17 Jul 2023 | 17 Jul 2023 | Due to the Prevailing Pandemic situation, more than three months labours & materials were not available on site. |
Located at Ambarnath, Ambarnath, Andheri, Mumbai Suburban, 421501. Per the filed land record, the plot is bounded to the north by Sai Ahray Dev Wing L, to the south by 18 Mtr Proposed Road, to the east by Sai Ashray Dev Wing N O P and Q and to the west by Sai Ashray Dev Wing I. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 33 km |
| Andheri MIDC / SEEPZ | 36 km |
| Chhatrapati Shivaji Int'l Airport | 38 km |
| Bandra Kurla Complex (BKC) | 38 km |
| Lower Parel / Worli business district | 45 km |
| Nariman Point / Fort | 50 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in PRASADAM- PHASE IV- WING J K AND M?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
SAI Ashray Developers PVT LTD is the promoter on 6 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026