PRASADAM - PHASE VII- WING F AND G

Ambarnath · SAI ASHRAY DEVELOPERS PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700005479

Delivery and registration

When is the project declared for completion?

PRASADAM - PHASE VII- WING F AND G is registered with MahaRERA as P51700005479 and the promoter has declared completion for 30 Jan 2024.

30 Jan 2024

declared completion

32months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700005479
Registered on11 Aug 2017
Promoter-declared completion30 Jan 2024
Current statusCertificate Signed
Against todayabout 32 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PRASADAM - PHASE VII- WING F AND G record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Ashray Developers is the promoter of record on 23 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

23projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PRASADAM - PHASE VII- WING F AND G in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
PRASADAM WING FG1G+831 Jan 2022

Legal and disputes

What disputes are disclosed?

9 complaints are on the MahaRERA record for PRASADAM - PHASE VII- WING F AND G, with orders passed in 8 of them.

9complaints

8with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005653811/10/2018Haresh Rawtani vs Sai Ashray Developes Pvt. Ltdorder passed
CC00600000005691914/11/2018SEEMA B RANA vs SAI ASHRAY DEVELOPERS PVT. LTD.order passed
CC00600000017153113/11/2019Pragnya Shetty vs Sai Ashray Developers Pvt.Ltd (Ahuja Group)order passed
CC00600000039673506/09/2023Shubhangi Rajendra Singh vs SAI ASHRAY DEVELOPERS PVT LTDorder passed
CC00600000039734704/09/2023Rominder Singh Dhonsi vs Sai Ashray Developers pvt Ltd.order passed
CC00600000039739907/09/2023MAHAVIR RAMNIKLAL SHAH vs SAI ASHRAY DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000039764721/10/2023Harshal Amarnath Salian vs sai ashray developers pvt ltdorder passed
CC00600000039765129/09/2023Rajvi Hetalkumar Shah vs Sai Ashray Developers Pvt. Ltd.order passed
CC1260125908/03/2026Brishketu Ramprakash Singh vs SAI ASHRAY DEVELOPERS PVT LTDpending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Ulhasnagar3712015Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jan 2024Due to the Prevailing Pandemic situation, more than many months labours & materials were not available on site.

Location, Land & Connectivity

Located at Ambarnath, Ambarnath, Andheri, Mumbai Suburban, 421501. Per the filed land record, the plot is bounded to the north by 18 Mtr Proposed Road, to the south by Sai Ashray Dev Wing J, to the east by Sai Ashray Dev Wing J and K and to the west by S No 78-8 Pt. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park33 km
Andheri MIDC / SEEPZ36 km
Chhatrapati Shivaji Int'l Airport38 km
Bandra Kurla Complex (BKC)38 km
Lower Parel / Worli business district45 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI Ashray Developers PVT LTD is the promoter on 6 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by SAI Ashray Developers PVT LTD

SAI Ashray Developers PVT LTD
Past its declared completion dateThane
SAI Ashray Developers PVT LTD
Past its declared completion dateThane
SAI Ashray Developers PVT LTD
Past its declared completion dateThane
SAI Ashray Developers PVT LTD
Past its declared completion dateThane
SAI Ashray Developers PVT LTD
Past its declared completion dateThane

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

Pratapgad By Bhagwati Haware – Wing - C
possession by Dec 2032 · Bhagwati Haware Properties Supertech
Prathamesh Darshan
possession by Mar 2027 · Built IN Reality Pratham
Prathamesh Plaza
declared completion Feb 2021 · MS. Tirupaticonstruction
Prathmesh
declared completion Dec 2022 · Axis Builders PVT LTD
Prathmesh Vrindavan F Wing
possession by Dec 2026 · S. P. Group
Pratik Greens-2
possession by Dec 2031 · Shirvawala Estate Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026