MahaRERA Property Intelligence · Thane

PRASADAM- PHASE VI-WING H I AND L

P51700005650 · Ambarnath · promoter Sai Ashray Developers

Certificate SignedDue 28 Aug 2023

Delivery & Registration

MahaRERA registrationP51700005650
Registered on11 Aug 2017
Promoter-declared completion28 Aug 2023
Current statusCertificate Signed
Against todayabout 35 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sai Ashray Developers is the promoter of record on 23 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
PRASADAM WING HIL1G+828 Aug 2022

Complaints & Orders

8 complaints are on the MahaRERA record for this project, with orders passed in 7. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019890402/11/2021RICHA BHUVNESHWAR PATHAK vs Darshana Anand Damle & Ashish Anand Damleorder passed
CC00600000023120117/05/2022Abhishek Shukla vs Sai Ashray Developer Pvt. Ltd.order passed
CC00600000025150318/06/2022Mr. Girish Hiralal Lalwani Mrs. Barkha Girish Lalwani Mr. Prithvi Girish Lalwani vs M/s Ahuja Properties And Associatesorder passed
CC00600000036476311/03/2023jagdevi nagnath mangrule vs SAI ASHRAY DEVELOPERS PVT LTDorder passed
CC00600000039774308/02/2024PRAKASH DINDAYAL KHATRI vs SAI ASHRAY DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000053069218/06/2024KRISHNAKUMAR TEJBAHDUR SINGH vs M/S SAI ASHRAY DEVELOPERS PRIVATE LIMITEDorder passed
CC1250243217/07/2025Shrinivas Sathaiah Chowki vs SAI ASHRAY DEVELOPERS PVT LTDorder passed
CC1260381020/06/2026Bhavana Vishal patil vs SAI ASHRAY DEVELOPERS PVT LTDpending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Ulhasnagar3712015Pending

Location, Land & Connectivity

Located at Ambarnath, Ambarnath, Andheri, Mumbai Suburban, 421501. Per the filed land record, the plot is bounded to the north by 18 Mtr Proposed Road, to the south by Sai Ashray Dev Wing J, to the east by Sai Ashray Dev Wing N and O and to the west by S No 74-8 Pt. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park33 km
Andheri MIDC / SEEPZ36 km
Chhatrapati Shivaji Int'l Airport38 km
Bandra Kurla Complex (BKC)38 km
Lower Parel / Worli business district45 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI Ashray Developers PVT LTD is the promoter on 6 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by SAI Ashray Developers PVT LTD

SAI Ashray Developers PVT LTD
Past its declared completion dateThane
SAI Ashray Developers PVT LTD
Past its declared completion dateThane
SAI Ashray Developers PVT LTD
Past its declared completion dateThane
SAI Ashray Developers PVT LTD
Past its declared completion dateThane
SAI Ashray Developers PVT LTD
Past its declared completion dateThane

Other RERA-registered projects in Ambernath

24 High Bizbay
possession by Jul 2026 · Apex Infra
Shree Gajanan Enterprises Rukhmini CHS
possession by Jul 2026 · Shree Gajanan Enterprises Rukhmini CHS
Walekar Homes
possession by Aug 2026 · Walekar & Son's Developers
Patels Eirene
possession by Aug 2026 · Pramukh Developers
Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters

Major developers building in Ambernath

Other RERA-registered projects in Thane

Prasadam - Phase VII- Wing F AND G
declared completion Jan 2024 · SAI Ashray Developers PVT LTD
Pratapgad By Bhagwati Haware – Wing - C
possession by Dec 2032 · Bhagwati Haware Properties Supertech
Pratham Heights
declared completion Dec 2017 · Pratham Infrastructure
Prathamesh Chsl
declared completion Jun 2025 · Nirmal Developers
Prathamesh Darshan
possession by Mar 2027 · Built IN Reality Pratham
Prathamesh Plaza
declared completion Feb 2021 · MS. Tirupaticonstruction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026