MahaRERA Property Intelligence · Thane

PRIME BALAJI HEIGHT

P51700010278 · promoter Prime Housing

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51700010278
Registered on24 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Prime Housing is the promoter of record on 129 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
A WING1G+830 Jun 2021
B WING1G+1030 Jun 2021

Complaints & Orders

6 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019297218/03/2020Suresh Narayan Dalvi vs M/s Prime Housingorder passed
CC00600000019572723/01/2021Supriya Suresh Dalvi vs Prime Housingorder passed
CC00600000019572823/01/2021Supriya Suresh Dalvi vs Prime Housingorder passed
CC1240022825/09/2024Shayam Sundar Tilak Jaiswal vs PRIME HOUSINGpending / no order on file
CC1240023726/09/2024DILIP KUMAR CHAUDHARY vs PRIME HOUSINGpending / no order on file
CC1260278613/05/2026Dhanshree Dhruvabal Chavan vs PRIME HOUSINGpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202330 Dec 2020As per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.12.2019 as the project completion date. However, we were not ab
30 Dec 202330 Jun 2023The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of the pandemic of Covid-19. We are on the

Location, Land & Connectivity

Located at Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by SURVEY NO 133-3, to the south by SURVEY NO 139-4, to the east by SURVEY NO 139-3 and to the west by SURVEY NO 139-1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~38 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park38 km
Andheri MIDC / SEEPZ41 km
Chhatrapati Shivaji Int'l Airport42 km
Bandra Kurla Complex (BKC)42 km
Lower Parel / Worli business district49 km
Nariman Point / Fort53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Prime Housing is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Prime Housing

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Prime Heights
possession by Feb 2029 · Prime Enterprises
Prime Kingdom
possession by Dec 2036 · Prime Core Builders LLP
Prime Nest
declared completion Dec 2025 · Magnus Enterprises
Primera
possession by Dec 2029 · Agile Real Estate Dev Private Limited
Primrose Mhada 2
declared completion Mar 2025 · Runwal Residency Private Limited
Primus Business Park
declared completion Oct 2022 · Hemant Kashikar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026