Mumbai/Project record

MahaRERA · the public record

RAJESH CO-OPERATIVE HOUSING SOCIETY

Thane · JOSHI ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700005908

Delivery and registration

When is the project declared for completion?

RAJESH CO-OPERATIVE HOUSING SOCIETY is registered with MahaRERA as P51700005908 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700005908
Registered on14 Aug 2017
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAJESH CO-OPERATIVE HOUSING SOCIETY record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Joshi Enterprises is the promoter of record on 98 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

98projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAJESH CO-OPERATIVE HOUSING SOCIETY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
RAJESH CO-OPERATIVE HOUSING SOCIETY1G+1031 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2020FORM E & EXPLANATORY NOTE EXPLAINING REASONS FOR EXTENSION IS SEPARATELY ATTACHED WITH SUPPORTING DOCUMENTS Contents of this note are reproduced below: Explanatory note regarding
31 Jul 202031 Mar 2023MAHARERA has issued certificate of registration of the project dated 14th August 2017 in which the original proposed date of completion of project was 8th August 2019. Thereafter w

Location, Land & Connectivity

Located at Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by PLOT NO 11 OWNED BY 10 OWNERS, to the south by S NO 359P AS GOVERNMENT, to the east by PLOT NO 2 OWNED BY RUBA CHS and to the west by PLOT NO 4 OWNED BY V D JOSHI AND V V JOSHI. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park10 km
Andheri MIDC / SEEPZ12 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district26 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Joshi Enterprises is the promoter on 11 MahaRERA-registered projects, of which 8 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Joshi Enterprises project & its RERA track record →

Other flagged projects by Joshi Enterprises

Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Not filing quarterly progress reportsThane
Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Not filing quarterly progress reportsThane

Other RERA-registered projects in Naupada

Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers

Major developers building in Naupada

Other RERA-registered projects in Thane

Rajeshwari Co Op Housing Society Ltd
possession by Mar 2030 · Rajeshwari Co Op Housing Society Ltd
Rajeshwari Complex
possession by Dec 2027 · Manohar Vithu Chaudhari
Rajeshwari Plaza
possession by Mar 2027 · Sheela Ravindra Ghormode
Rajeshwari Residency Phase II
possession by Dec 2027 · Shree Siddhi Construction
Rajgad By Bhagwati Haware – Wing - D
possession by Dec 2032 · Bhagwati Haware Properties Supertech
Rajlaxmi Developers
declared completion Apr 2024 · Rajlaxmi Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026