Mumbai/Project record

MahaRERA · the public record

Nutan Co-Operative Housing Society Ltd.

Naupada · JOSHI ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700023800

Delivery and registration

When is the project declared for completion?

Nutan Co-Operative Housing Society Ltd. is registered with MahaRERA as P51700023800 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700023800
Registered on06 Jan 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Nutan Co-Operative Housing Society Ltd. record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Joshi Enterprises is the promoter of record on 98 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

98projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Nutan Co-Operative Housing Society Ltd. in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Nutan Co-Operative Housing Society1G+831 Dec 2022

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Nutan Co-Operative Housing Society Ltd., with orders passed in 2 of them.

5complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039546502/05/2023SANJAY SURESH RANADE vs KAUSTUBH KALKEorder passed
CC00600000042934320/02/2024sukrut suresh paranjape vs m/s joshi enterprisesorder passed
CC1250224805/07/2025Prajakta Bandish Tamhankar vs JOSHI ENTERPRISESpending / no order on file
CC1260248728/04/2026Maruti Laxman Sawant vs JOSHI ENTERPRISESpending / no order on file
CC1260249428/04/2026Manish Ravji Saiya vs JOSHI ENTERPRISESpending / no order on file

Location, Land & Connectivity

Located at Naupada, 6.00 M. Wide Road, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by Indraprasth Building, to the south by Neroy Property, to the east by Indraprasth Building and to the west by New Suyash Property. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Joshi Enterprises is the promoter on 11 MahaRERA-registered projects, of which 8 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Joshi Enterprises project & its RERA track record →

Other flagged projects by Joshi Enterprises

Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Not filing quarterly progress reportsThane
Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Not filing quarterly progress reportsThane

Other RERA-registered projects in Naupada

Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers

Major developers building in Naupada

Other RERA-registered projects in Thane

Nutan Omkar Vihar
declared completion Aug 2022 · Omkar Enterprises
O22 Business Park
possession by Dec 2026 · Midas Touch
OAK Leaf Towers
possession by Dec 2030 · Axis Housing Private Limited
Oasis Habitats
declared completion Jun 2026 · Faisal Nisar Ahmed Shaikh
Ocean Developers
declared completion Dec 2023 · Prashant Valki Mali
Ocean Green
possession by Dec 2030 · A.k. Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026