MahaRERA Property Intelligence · Mumbai Suburban

Redevelopment of Juhu Shantivan CHSL

P51800001772 · 5th cross road · promoter Shree Mahavir Properties

Certificate SignedDue 30 Sep 2020

Delivery & Registration

MahaRERA registrationP51800001772
Registered on29 Jul 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Mahavir Properties is the promoter of record on 125 projects, of which 9 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
Redevelopment of Juhu Shantivan CHSL1G+1831 Mar 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202030 Mar 2020We hereby request you to grant extension of registration for project ‘Redevelopment of Juhu Shantivan CHSL’ situated at CTS No. 25A at Greater Mumbai (M Corp.) (Part) (802794), Mum

Location, Land & Connectivity

Located at 5th cross road, Gulmohar Road, Mumbai, Mumbai Suburban, 400049. Per the filed land record, the plot is bounded to the north by 30 feet wide road, to the south by 30 feet wide road, to the east by Bldg 12 River Heaven CHSL and to the west by Bldg No 14 Kadambari CHSL. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport4 km
Andheri MIDC / SEEPZ4 km
Bandra Kurla Complex (BKC)6 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district13 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Juhu

Elenora
possession by Sep 2026 · Parinee VIR Bhuvan Redevelopment Private
K L Valeria
possession by Sep 2026 · K L Housing LLP
Valletta
possession by Sep 2026 · K Raheja Corp Real Estate Private Limite
Maestro
possession by Nov 2026 · K Raheja Corp Real Estate Private Limite
Aditya Chsl
possession by Dec 2026 · Shree Mahavir Developers
Gurukrupa Alaknanda
possession by Dec 2026 · Gurukrupa Realcon Infrastructure Develop

Major developers building in Juhu

Other RERA-registered projects in Mumbai Suburban

Redevelopment OF Kaveri Chsl
possession by Mar 2028 · Pranav Constructions Limited
Redevelopment OF Kesar Niketan Chsl
declared completion Jan 2026 · Pranav Constructions Limited
Redevelopment OF Khatri Apartments Cooperative Housing Society Limited
declared completion Jun 2024 · SRP Realtors Privaye Limited
Redevelopment OF Kripadham CHS LTD
declared completion Dec 2017 · Kripa Realtors
Redevelopment OF Lakshman Tower Chsl
possession by Mar 2027 · Pranav Constructions Limited
Redevelopment Of Lamplight Chsl
declared completion Dec 2021 · Shree Mahavir Estates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026