Redevelopment of Link Palace Premises Co-Op Soc. Ltd. Phase I

P51800008272 · promoter Kolte-Patil

Certificate SignedDue 31 Mar 2018

Delivery & Registration

MahaRERA registrationP51800008272
Registered on18 Aug 2017
Promoter-declared completion31 Mar 2018
Current statusCertificate Signed
Against todayabout 100 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kolte-Patil is the promoter of record on 82 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Link Palace1G+1331 Mar 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 201831 Mar 2018The construction of the buildings forming part of the Project have been completed in all respect as per the sanctioned layout plans. No work is pending to be completed. In light of

Location, Land & Connectivity

Located at Pune City, Pune, 400054. Per the filed land record, the plot is bounded to the north by Plot No 63G, to the south by Plot No 63 Part, to the east by Plot No 63G and 63H and to the west by Vithaldas Patel Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)4 km
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park9 km
Lower Parel / Worli business district9 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Builder track record

Kolte-Patil Developers Limited is the promoter on 55 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Kolte-Patil Developers Limited project & its RERA track record →

Other flagged projects by Kolte-Patil Developers Limited

Kolte-Patil Developers Limited
FlaggedMumbai Suburban
Kolte-Patil Developers Limited
FlaggedMumbai Suburban
Kolte-Patil Developers Limited
FlaggedMumbai Suburban
Kolte-Patil Developers Limited
FlaggedMumbai Suburban
Kolte-Patil Developers Limited
FlaggedMumbai Suburban
Kolte-Patil Developers Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai Suburban

Redevelopment OF Loita Kunj CHS LTD
declared completion Dec 2025 · Orra Realtors Private Limited
Redevelopment OF Malad Ajanta CHS
possession by Dec 2026 · Nareshbhai Vallabhbhai Patel
Redevelopment OF Malad Amber Chsl
declared completion Oct 2023 · Pranav Constructions Limited
Redevelopment Of Malad Jay Amrat Co-Operative Housing Society-Rishab Jay Amrat
declared completion Jun 2023 · Rishabraj Toughcons City Homes Private L
Redevelopment OF Malad Marudhar Chsl
declared completion Jan 2025 · Pranav Constructions Limited
Redevelopment OF Malad Rajhans Chsl
declared completion Mar 2019 · Pranav Constructions Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026