MahaRERA · the public record
Royal Fantasy Phase III
Andheri · Royal Fantasy Constructions Private Limited
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51800009920
Delivery and registration
When is the project declared for completion?
Royal Fantasy Phase III is registered with MahaRERA as P51800009920 and the promoter has declared completion for 30 Jun 2026.
30 Jun 2026
declared completion
3months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51800009920 |
| Registered on | 22 Aug 2017 |
| Promoter-declared completion | 30 Jun 2026 |
| Current status | Certificate Signed |
| Against today | about 3 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Royal Fantasy Phase III record 34 quarterly progress reports since registration.
34quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 34 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Royal Fantasy Constructions is the promoter of record on 4 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
4projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In Royal Fantasy Phase III, ₹45.69 Cr of a declared ₹49.40 Cr estimated project cost is reported as incurred, about 92.5%, as at the last certified filing with MahaRERA.
92.5%
₹45.69 Cr
of ₹49.40 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Royal Fantasy Phase III, 50 of 60 homes filed with MahaRERA are recorded as sold or booked (47 with registered agreements and 3 booked), about 83%, and 10 remain available.
83%sold
50 of 60 homes
₹76.28 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹61.48 Cr (about 81%) is recorded as collected and ₹14.80 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 50 registered agreements, the effective carpet rate is ₹17,686/sqft, with eight in ten falling between ₹14,662 and ₹21,846 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.
| Floor | Unit | Carpet | Govt reckoner value |
|---|---|---|---|
| Floor 11 | Height A-Wing (Hostel Building) 11th Floor | 712 sqft (66.12 sqm) | ₹1.34 Cr |
| Floor 12 | Height B-1202 | 473 sqft (43.92 sqm) | ₹88.97 Lakh |
| Floor 14 | Height B-1402 | 473 sqft (43.92 sqm) | ₹88.97 Lakh |
| Floor 14 | Height B-1403 | 289 sqft (26.85 sqm) | ₹54.39 Lakh |
| Floor 14 | Height B-1404 | 465 sqft (43.19 sqm) | ₹87.49 Lakh |
| Floor 15 | Height B-1502 | 473 sqft (43.92 sqm) | ₹88.97 Lakh |
| Floor 15 | Height B-1504 | 465 sqft (43.19 sqm) | ₹87.49 Lakh |
| Floor 15 | Height B-1505 | 678 sqft (62.98 sqm) | ₹1.28 Cr |
| Floor 3 | D-201 | 712 sqft (66.12 sqm) | ₹1.22 Cr |
| Floor 3 | D-205 | 712 sqft (66.12 sqm) | ₹1.22 Cr |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 16 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 50 homes carry one, and 9 of the 60 are recorded unsold. Since we started watching this ledger, 1 home has moved out of the unsold list, most recently on 08 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| Height A-Wing (Hostel Building) 11th Floor | 712 sqft | Rs 1.3105 cr typical, over Rs 90.50 lakh to Rs 1.6910 cr | 23 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Royal Fantasy Phase III, 3 of the 9 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15 and 60 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Dreamax Height Wing C PTC Slab 13th to 15th - no Saleable | 1 | G+3 | 1 | - |
| Dreamax Height Wing A PH Full - no Saleable | 1 | G+15 | 11 | - |
| Dreamax Vega Wing D | 1 | G+15 | 40 | - |
| Dreamax Height Wing B 12th - 15th floor | 1 | G+4 | 8 | - |
Unit mix on the filing: 59 residential and 1 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 5 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Dec 2020 | Our under construction real estate project is getting delayed due to several reasons as follows: 1. Temporary Negative cash flow due to, • Buyers not paying dues on time • finan |
| 30 Dec 2020 | 30 Jun 2023 | 1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to i |
| 30 Jun 2023 | 30 Jun 2024 | 1. Temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale 2. Shortage of labour, disruptions due to implementation of GST & continu |
| 30 Jun 2024 | 30 Jun 2025 | 1. Work in progress in phase 3 is slow as compared to our schedule because we have to take utmost care of possession given to flat buyers in phase 1 close to the phase 3 building d |
| 30 Jun 2025 | 30 Jun 2026 | i) The project comprises three phases—Phase 1, Phase 2, and Phase 3—being developed on the same plot of land and includes two buildings: Dreamax Vega and Dreamax Height. Phase 1 ha |
Location, Land & Connectivity
Located at Andheri, Andheri, Andheri, Mumbai Suburban, 400093. Per the filed land record, the plot is bounded to the north by Plot Bearing No 386-286-368-287-368-292, to the south by Plot Bearing No 368-295A-368-295C, to the east by Plot Bearing No 368-254 and to the west by Plot Bearing No 383-397-397A-423. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 1 km |
| Chhatrapati Shivaji Int'l Airport | 4 km |
| Powai / Hiranandani business park | 5 km |
| Bandra Kurla Complex (BKC) | 7 km |
| Lower Parel / Worli business district | 15 km |
| Nariman Point / Fort | 23 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.