MahaRERA Property Intelligence · Mumbai Suburban

SABARI HORIZON

P51800003677 · Mumbai · promoter Sabari Developers Llp

Certificate SignedDue 30 Oct 2020

Delivery & Registration

MahaRERA registrationP51800003677
Registered on06 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sabari Developers Llp is the promoter of record on 9 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
SABARI HORIZON1G+2031 May 2019

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005497518/06/2018Mr. Kishorchandra P. Sampat vs Sabari Developers LLPorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Oct 202030 Apr 2020Project had to be Approved under DCPR 2034 and hence approval was delayed.

Location, Land & Connectivity

Located at Mumbai, Chembur, Kurla, Mumbai Suburban, 400088. Per the filed land record, the plot is bounded to the north by CTS No 421 , to the south by CTS NO 423 A AND B, to the east by NALA and to the west by CTS NO 422 B. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)7 km
Chhatrapati Shivaji Int'l Airport8 km
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Lower Parel / Worli business district12 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sabari Developers LLP is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Sabari Developers LLP

Sabari Developers LLP
FlaggedMumbai Suburban
Sabari Developers LLP
FlaggedMumbai Suburban
Sabari Developers LLP
FlaggedMumbai Suburban
Sabari Developers LLP
FlaggedMumbai Suburban
Sabari Developers LLP
FlaggedMumbai Suburban

Other RERA-registered projects in Deonar

Jai Kamal
possession by Aug 2026 · Ameet Infra
Surve Tower
possession by Dec 2026 · Meena Vikas Raikar
Gagan Giri Co-Operative Housing Society Limited
Not filing quarterly progress reports · possession by Dec 2026 · Mishal Construction Private Limited
Shilpadatta By Sandu Developers
possession by Dec 2026 · Sandu Developers Pvt. Ltd.
Akshar Amar Mansion
possession by Mar 2027 · Akshar Properties
Anuvidnyan Nagar Co-Op. Housing Society Ltd
possession by Jun 2027 · Makwise Homes LLP

Major developers building in Deonar

Other RERA-registered projects in Mumbai Suburban

Sabari Mira
possession by Dec 2026 · Sabari Urban Developers LLP
Sabari Palm View
declared completion Mar 2019 · Sabari Developers LLP
Sabari Sangam Wing A
declared completion Dec 2018 · Meraki Habitats LLP
Sabari Shaan
declared completion Dec 2018 · Shankheshwar Properties Pvt Ltd
Sabari Shobha
declared completion Nov 2021 · Sabari Developers LLP
Sach Splendid
possession by Apr 2027 · Sach Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026