MahaRERA Property Intelligence · Mumbai Suburban

SAFAL TRADEMARK

P51800003754 · CHEMBUR · promoter Jai Mata Di

Certificate SignedDue 31 May 2026

Delivery & Registration

MahaRERA registrationP51800003754
Registered on06 Aug 2017
Promoter-declared completion31 May 2026
Current statusCertificate Signed
Against todayabout 2 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Jai Mata Di is the promoter of record on 45 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~85.8% of the estimated project cost incurred as of the last certificate (₹135.50 Cr spent against a ₹158.00 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~85.8% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 230 homes filed with MahaRERA, 212 are sold/booked and 18 remain available (~92% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹348.18 Cr in agreement value so far. Of that, ₹265.16 Cr (~76%) is already collected, ₹83.02 Cr receivable — a read on how far along these sales really are. Note: the project registers 252 homes in total, but this sold/unsold inventory filing covers only 230 of them — the other 22 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 212 registered agreements, the effective carpet rate is ₹20,451/sqft (typical range ₹17,773–₹29,736) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1TOWER 3-102696 sqft (64.68 sqm)₹1.33 Cr
Floor 10TOWER 4-1003750 sqft (69.71 sqm)₹1.50 Cr
Floor 10TOWER 4-1004752 sqft (69.82 sqm)₹1.51 Cr
Floor 12TOWER 2-1201782 sqft (72.64 sqm)₹1.64 Cr
Floor 12TOWER 2-12021,094 sqft (101.6 sqm)₹2.30 Cr
Floor 12TOWER 4-1201636 sqft (59.13 sqm)₹1.34 Cr
Floor 13TOWER 1-13031,041 sqft (96.67 sqm)₹2.19 Cr
Floor 15TOWER 1-1501744 sqft (69.12 sqm)₹1.56 Cr
Floor 15TOWER 1-15021,048 sqft (97.37 sqm)₹2.20 Cr
Floor 2TOWER 1-2031,041 sqft (96.67 sqm)₹1.99 Cr
Floor 3TOWER 2-301782 sqft (72.64 sqm)₹1.49 Cr
Floor 4TOWER 1-4031,041 sqft (96.67 sqm)₹1.99 Cr
Floor 4TOWER 3-401991 sqft (92.11 sqm)₹1.89 Cr
Floor 6TOWER 1-6031,041 sqft (96.67 sqm)₹2.09 Cr
Floor 6TOWER 3-601991 sqft (92.11 sqm)₹1.99 Cr
Floor 6TOWER 3-603749 sqft (69.57 sqm)₹1.50 Cr
Floor 8TOWER 4-801636 sqft (59.13 sqm)₹1.28 Cr
Floor 9TOWER 4-903750 sqft (69.71 sqm)₹1.50 Cr

⚠ The inventory filing also declares: 4 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19 and 252 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SAFAL TRADEMARK TOWER 1,2,3 4 WAMANDEV1G+19252-

Unit mix on the filing: 252 residential.

Complaints & Orders

30 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1240125127/12/2024Sumeet Ramnath Nayak vs JAI MATA DI HOME CONSTRUCTION PVT LTDorder passed
CC1250111803/04/2025MANISH SINGHVI vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250160415/05/2025PRITHIPAL SINGH BHAMBRA vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250163921/05/2025HARLEEN PASRICHA vs JAI MATA DI HOME CONSTRUCTION PVT LTDorder passed
CC1250164021/05/2025MANINDER PASRICHA vs JAI MATA DI HOME CONSTRUCTION PVT LTDorder passed
CC1250204523/06/2025Sonal Sharma vs JAI MATA DI HOME CONSTRUCTION PVT LTDorder passed
CC1250258627/07/2025Rakesh Prakash Bhat vs JAI MATA DI HOME CONSTRUCTION PVT LTDorder passed
CC1250258727/07/2025Sharad Nagesh Shenoy vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250258927/07/2025Shankar Jagtap vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250250921/07/2025Deep Mukherjee vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250262530/07/2025Rajesh Bhatia vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250259127/07/2025Rahul Rajanikant Pathak vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250259328/07/2025Deepak Prakash Gurnane vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250260328/07/2025Sonali Melmane vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250262630/07/2025Amit Chanda vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250260728/07/2025Ronak Johari vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250262730/07/2025Offshore Infrastructures Limited vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250259227/07/2025Amit Gulshan Talwar vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250259428/07/2025Sethu naga muthu Rakkumuthu Thangavelu vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250336921/09/2025Neha Chendvankar vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250340923/09/2025Unita Agatha Dmello vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250351702/10/2025Rajesh Chander Jagasia vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250355907/10/2025Jagan Ramaswamy vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250352303/10/2025Umesh Ravindra Gupta vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250352403/10/2025Shailendra Surendra Gupta vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250384902/11/2025Bina Vijay Patel vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1250384802/11/2025Vijay Ambalal Patel vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1260057402/02/2026Arvind Setia vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1260162623/03/2026Mona Ajay Kakar vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file
CC1260124507/03/2026Sunil Kumar Singh vs JAI MATA DI HOME CONSTRUCTION PVT LTDpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Aug 202431 Aug 2024THE LOCKDOWNS LED TO CONSTRUCTION ACTIVITIES COMING TO A STANDSTILL DUE TO NON-AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PR
30 Dec 202331 Mar 2025DUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS NOT COMPLETED THEREFORE REQUIRE EXTENSION UPTO 31ST MARCH 2025.
30 Dec 202331 Dec 2025DUE TO UNRESOLVED FINANCIAL CONSTRAINTS FACED , CONSTRUCTION WORK OF THE BUILDINGS ARE NOT COMPLETED . THEREFORE, WE REQUIRE ADDTIONAL TIME I.E EXTENSION UPTO 31ST DECEMBER 2025 TO
30 Dec 202331 May 2026Due to financial constraints faced by us, the progress of the project was temporarily affected. We wish to inform you that all financial issues have now been resolved, and construc

Location, Land & Connectivity

Located at CHEMBUR, V.N.PURAV MARG, Kurla, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by BY ROAD AND CTS NO 336, to the south by BY CTS 304 TO 310, to the east by BY CTS NO 325 394 313 312 and to the west by BY CTS NO 300 301 302. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district9 km
Andheri MIDC / SEEPZ9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

JAI Mata DI Home Construction PVT LTD is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by JAI Mata DI Home Construction PVT LTD

JAI Mata DI Home Construction PVT LTD
FlaggedMumbai Suburban

Other RERA-registered projects in Chembur

Chembur Deep Jyoti CHS LTD
possession by Jul 2026 · P M Developers
Hubtown Seasons - B Wing
possession by Jul 2026 · Joynest Premises Privatelimited
Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Safalya
declared completion Jun 2018 · Vitae Constructions LLP
Safalya
declared completion Sep 2022 · Vijay Mallya
Safavi CHS LTD
declared completion Oct 2020 · RAJ Builders
Saffron Heights
declared completion Oct 2023 · Pratham Varadvinayak Developers LLP
Saffron Peace
possession by Dec 2027 · Rishabraj Namo Enterprise LLP
Saffron Residency Phase -1
possession by Dec 2026 · Ayodhya Construction CO

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026