MahaRERA · the public record
SAFAL MONTBAY
DEONAR MUMBAI · JAI MATA DI HOME CONSTRUCTION PVT LTD
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Sep 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51800028789
Delivery and registration
When is the project declared for completion?
SAFAL MONTBAY is registered with MahaRERA as P51800028789 and the promoter has declared completion for 30 Sep 2028.
30 Sep 2028
declared completion
24months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51800028789 |
| Registered on | 30 Mar 2021 |
| Promoter-declared completion | 30 Sep 2028 |
| Current status | Certificate Signed |
| Against today | 24 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAFAL MONTBAY record 25 quarterly progress reports since registration.
25quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Jai Mata Di is the promoter of record on 47 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
47projects
registered with MahaRERA
4flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for SAFAL MONTBAY in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| SAFAL MONTBAY WING A | 1 | G+19 | - |
| SAFAL MONTBAY WING B | 1 | G+19 | - |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Sep 2028 | Due to financial constraints faced by us, the construction activity is not completed we therefore request for extension upto September 2028. |
Location, Land & Connectivity
Located at DEONAR MUMBAI, S T ROAD, Kurla, Mumbai Suburban, 400088. Per the filed land record, the plot is bounded to the north by CTS NO 390B VAIBHAV INDUSTRIAL ESTATE, to the south by CTS NO 391 SAI SANSKAR CHS, to the east by 10 MT WIDE RAHEJA ACROPOLIS RD and to the west by CTS NO 394 AND 395. These are the boundaries as recorded in the filed land record.