MahaRERA · the public record
SAI VIHAR RESIDENCY
BHIWANDI · N M DEVELOPERS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
28 Feb 2022
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700017382
Delivery and registration
When is the project declared for completion?
SAI VIHAR RESIDENCY is registered with MahaRERA as P51700017382 and the promoter has declared completion for 28 Feb 2022.
28 Feb 2022
declared completion
55months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700017382 |
| Registered on | 09 Aug 2018 |
| Promoter-declared completion | 28 Feb 2022 |
| Current status | Certificate Signed |
| Against today | about 55 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI VIHAR RESIDENCY record 15 quarterly progress reports since registration.
15quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for SAI VIHAR RESIDENCY in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Sai Vihar Residency | 1 | G+5 | 30 Sep 2020 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 28 Feb 2022 | WE HAVE COMPLETED 95% CONSTRUCTION WORK OF OUR PROJECT, BUT DUE TO FORCE MAJEURE LIKE COVID-19 PANDEMIC SITUATION, WE WERE UNABLE TO COMPLETE THE PROJECT WITHIN STIPULATED TIME PER |
Location, Land & Connectivity
Located at BHIWANDI, FENE, Bhiwandi, Thane, 421302. Per the filed land record, the plot is bounded to the north by Road, to the south by Road, to the east by Gully and Pandurang Patil House and to the west by Road and Gokul Patil House. These are the boundaries as recorded in the filed land record.