Satellite Elegance

P51800021913 · Goregoan East · promoter Newone Constructions Private

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51800021913
Registered on08 Aug 2019
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~64.7% of the estimated project cost incurred as of the last certificate (₹102.06 Cr spent against a ₹157.63 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 287 homes filed with MahaRERA, 267 are sold/booked (250 with registered agreements + 17 booked) and 20 remain available (~93% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹364.17 Cr in agreement value so far. Of that, ₹236.75 Cr (~65%) is already collected, ₹124.95 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 259 registered agreements, the effective carpet rate is ₹22,008/sqft (typical range ₹20,256–₹25,223) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 121202710 sqft (65.96 sqm)₹1.26 Cr
Floor 121203710 sqft (65.96 sqm)₹1.26 Cr
Floor 141402710 sqft (65.96 sqm)₹1.26 Cr
Floor 141403710 sqft (65.96 sqm)₹1.26 Cr
Floor 151502710 sqft (65.96 sqm)₹1.26 Cr
Floor 151503710 sqft (65.96 sqm)₹1.26 Cr
Floor 161602710 sqft (65.96 sqm)₹1.26 Cr
Floor 161603710 sqft (65.96 sqm)₹1.26 Cr
Floor 292901635 sqft (58.99 sqm)₹1.13 Cr
Floor 303002710 sqft (65.96 sqm)₹1.26 Cr
Floor 303003710 sqft (65.96 sqm)₹1.26 Cr
Floor 313103710 sqft (65.96 sqm)₹1.26 Cr
Floor 343401719 sqft (66.8 sqm)₹1.28 Cr
Floor 343402719 sqft (66.8 sqm)₹1.28 Cr
Floor 343403427 sqft (39.67 sqm)₹76.05 Lakh
Floor 343403794 sqft (73.77 sqm)₹1.41 Cr
Floor 343404714 sqft (66.33 sqm)₹1.27 Cr
Floor 343405453 sqft (42.09 sqm)₹80.68 Lakh
Floor 5502710 sqft (65.96 sqm)₹1.26 Cr
Floor 5504710 sqft (65.96 sqm)₹1.26 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+35 and 287 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Elegance Wing A1G+35144-
Elegance Wing B1G+35143-

Unit mix on the filing: 287 residential.

Complaints & Orders

10 complaints are on the MahaRERA record for this project, with orders passed in 7. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000050055325/05/2024NEWONE CONSTRUCTIONS PVT LTD NEWONE CONSTRUCTIONS PVT LTD vs SWAPNIL HIRAMAN PACHNEKARpending / no order on file
CC1250138826/04/2025Roshan Manjappa Salian vs Newone Constructions Private Limitedorder passed
CC1250139126/04/2025Roshan Manjappa Salian vs Newone Constructions Private Limitedorder passed
CC1250139326/04/2025Anand Vijay Raorane vs Newone Constructions Private Limitedorder passed
CC1250139526/04/2025Siddharth Sharadchandra Tiwari vs Newone Constructions Private Limitedorder passed
CC1250139626/04/2025Yuvraj Yogeshbhai Pandya vs Newone Constructions Private Limitedorder passed
CC1250139926/04/2025Shashwat Sanjay Goyal vs Newone Constructions Private Limitedorder passed
CC1250140326/04/2025SACHIN RAMCHANDRA SHINGARE vs Newone Constructions Private Limitedorder passed
CC1260175027/03/2026Anubhav Pansari vs Newone Constructions Private Limitedpending / no order on file
CC1260262305/05/2026Somanath sahoo vs Newone Constructions Private Limitedpending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High CourtPIL Lodging No 63 /20182018Not Admitted No Adverse Orders Passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202429 Dec 2025The project's completion date has been delayed mainly due to non-receipt of CC for part of 34th floor of project Satellite Elegance where MOEF/ EC clearance is mandatory. The reaso
30 Dec 202430 Jun 2026The reasons for seeking extension which were beyond the control of Newone Constructions Private Limited are briefly set out hereunder: 1. Final Commencement Certificate (CC) dela
30 Dec 202431 Dec 2026The reasons for seeking extension which were beyond the control of Promoter are briefly set out hereunder: 1. Final Commencement Certificate (CC) delayed (34th floor (Part) for MO

Location, Land & Connectivity

Located at Goregoan East, Pankaj Shah Marg, Opp Film City Road, Andheri, Mumbai Suburban, 400063. Per the filed land record, the plot is bounded to the north by CTS No 620 A 6, to the south by 13 mt wide Pankaj Shah Marg, to the east by CTS No 661 and to the west by CTS No 620A 6. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ5 km
Powai / Hiranandani business park7 km
Chhatrapati Shivaji Int'l Airport9 km
Bandra Kurla Complex (BKC)12 km
Lower Parel / Worli business district20 km
Nariman Point / Fort28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon East

Matrusmruti
possession by Oct 2026 · Gio Properties
Samarth Nandadeep Heights
possession by Oct 2026 · Samarth Tsquare
Onyx
possession by Nov 2026 · Shreeram Builders
Goregaon Adwait Chsl - Vijay Sadan
possession by Dec 2026 · Prashant Shirsat
Agarwal Floresta - Maple
possession by Dec 2026 · Homewell Realty LLP
Ashwin Heights
possession by Dec 2026 · Westinrely Developers PVT LTD

Major developers building in Goregaon East

Other RERA-registered projects in Mumbai Suburban

Satellite Glory
declared completion Dec 2020 · Satellite Developers PVT LTD
Satellite Heights
possession by Dec 2026 · Neeleshwar Developers
Sateri Legacy B Wing Phase I- 2nd And Above Floors
declared completion Dec 2023 · Bindra Sateri Constructions
Satguru CHS Ltd
declared completion Dec 2020 · Sai Tasveer Developers
Satguru Garden
declared completion Jul 2022 · Shree Satguru Developers
Satguru Heights
declared completion Jun 2024 · R.p. Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026